A seal structure for sealing between a through hole and a conduit located in the through hole. The seal structure includes a conduit located in the through hole and a foaming material. A wire is inserted in the conduit. The foaming material is located between the outer surface of the conduit and the inner surface of the through hole. The foaming material expands when heated and seals the space between the outer surface of the conduit and the inner surface of the through hole. Both ends of the conduit are sealed with a fireproof material between the inner surface of the conduit and the outer surface of the wire.
公开号:US20010001355A1
申请号:US09/285,856
申请日:1999-04-02
公开日:2001-05-24
发明作者:Shohachi Shimizu
申请人:Mirae Corp;
IPC主号:F16L5-04
专利说明:
[0001] The present invention relates to an apparatus and method for providing a sealed passage through partitions such as walls, floors, and ceilings for wires, pipes and the like. [0001]
[0002] FIG. 8 shows a prior art passage structure [0002] 37. The passage structure 37 is located in a through hole 34, which is formed in a partition such as a wall or a floor. The passage structure 37 includes a conduit 33 and fireproof material 35. The conduit 33 is inserted in the through hole 34 to pass through the partition 32. The fireproof material 35, which is material such as mortar or rock wool, fills the annular space between the outer surface of the conduit 33 and the inner surface of the through hole 34. A wire 36 passes through the conduit 33 and thus passes through the partition 32.
[0003] When the fireproof material [0003] 35 is put between the outer surface of the conduit 33 and the through hole 34, the pipe 33 must be retained at a certain position by a worker. The work is troublesome and difficult.
[0004] Generally, it takes two to three days for the fireproof material [0004] 35 to harden. The wire 36 cannot be inserted through the conduit 33 while the fireproof material 35 is hardening. This delays the construction work. There may be cases where the conduit 33 sinks in the fireproof material 35 due to its weight before the fireproof material 35 hardens. This produces a space between the conduit 33 and the fireproof material 35, and the conduit 33 is not firmly fixed in the partition 32. Further, extra work is necessary to fill the space with additional fireproof material 35. This lowers efficiency and increases construction costs. SUMMARY OF THE INVENTION
[0005] The objective of the present invention is to provide a partition passage and an installation method that efficiently and effectively produces sealed passage between an inner surface of a through hole and an outer surface of a conduit. [0005]
[0006] To achieve the above objective, the present invention provides a passage structure for permitting an object to pass through a partition. A through hole is formed in the partition. A conduit is located inside the through hole. A foaming material fills a space between the outer surface of the conduit and the inner surface of the through hole by expansion. The foaming material is expanded after the conduit is located in the through hole and the foaming material, after expanding, seals the space between the inner surface of the through hole and the outer surface of the conduit. [0006]
[0007] The present invention further provides a method for sealing a space between an inner surface of a through hole and an outer surface of a conduit. The through hole is formed in a partition. The method includes the following steps: inserting the conduit into the through hole; locating a foaming material between the inner surface of the through hole and the outer surface of the through member; and expanding the foaming material by stimulating reaction a reaction in the foaming material. [0007]
[0008] Other aspects and advantages of the present invention will become apparent from the following description, taken in conjunction with the accompanying drawings, illustrating by way of example the principles of the invention. [0008] BRIEF DESCRIPTION OF THE DRAWINGS
[0009] The features of the present invention that are believed to be novel are set forth with particularity in the appended claims. The invention, together with objects and advantages thereof, may best be understood by reference to the following description of the presently preferred embodiments together with the accompanying drawings in which: [0009]
[0010] FIG. 1 is a cross-sectional view showing a passage structure according to a first embodiment of the present invention; [0010]
[0011] FIG. 2 is a cross-sectional view showing a mold for forming a partition and a through hole in the partition; [0011]
[0012] FIG. 3 is a cross-sectional view showing the seal structure of FIG. 1 being heated during installation; [0012]
[0013] FIG. 4 is a cross-sectional view showing the passage structure of FIG. 3 after the installation is completed; [0013]
[0014] FIG. 5 is a cross-sectional view showing a passage structure according to a second embodiment of the present invention, with foaming material deposited after insertion of a conduit; [0014]
[0015] FIG. 6 is a cross-sectional view of a passage structure according to a third embodiment of the present invention; [0015]
[0016] FIG. 7([0016] a) is a cross-sectional view of a passage structure according to a fourth embodiment of the present invention prior to injection of foam passage structure;
[0017] FIG. 7([0017] b) is a cross-sectional view of the fourth embodiment after injecting foam passage structure; and
[0018] FIG. 8 is a cross-sectional view of a prior art passage structure. [0018] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0019] First Embodiment [0019]
[0020] A passage structure [0020] 19 according to a first embodiment of the present invention will now be described in reference to the drawings.
[0021] As shown in FIGS. 1 and 2, a through hole [0021] 13 is formed in a partition 12. The partition 12 may be a wall, floor, or ceiling of a building. A pipe form 14, which is part of a mold, is made of paper. As shown in FIG. 2, metal rings 15 are fitted on the outer surface of the pipe form 14. The cross-sectional shape of each metal ring is triangular.
[0022] The through hole [0022] 13 is formed when the partition 12 is formed. As shown in FIG. 2, wall forms 17 are arranged with a predetermined space in between. The pipe form 14 is located between the wall forms 17. Then, concrete is filled between the wall forms 17. The wall forms 17 are removed after the concrete hardens. Removing the pipe form 14 and the metal rings 15 leaves the through hole 13. A plurality of annular grooves 18 are formed on the inner surface of the through hole 13 by the metal rings 15. The cross sectional shape of the metal rings 15 is not limited to a triangular shape.
[0023] As shown in FIG. 3, the passage structure [0023] 19 includes a conduit 20, which is inserted in the through hole 13, and foaming material 21 is adhered on the outer surface of the conduit 20 near the center of the conduit 20. The conduit 20 is made of metal. As shown in FIG. 1, a wire 22 is inserted in the conduit 20. The surface of the conduit 20, to which the foaming material 23 adheres, is preferably knurled. The main component of the foaming material 21 is a synthetic mica that has swelling property and is dispersed or dissolved in alkaline salt solution. The swelling mica is a scale-like fine powder of a sodium-fluorine mica that is synthesized by a solid state reaction. The fine powder has an average particle diameter of 1-5 μm and a thickness of 10 angstroms. The swelling mica forms a complex by intercalating an inorganic or organic compound between its layers. A sodium silicate is used as the alkaline salt. GRANDEX (registered trademark) FJ515, a product of TOKIWA ELECTRIC Inc., is preferably used for the foaming material 21.
[0024] A method for manufacturing the foaming material [0024] 21 will now be described.
[0025] When the scale-shaped powder of the swelling mica is dispersed in a sodium silicate solution, water molecules are adsorbed between the layers of the swelling mica. This swells the swelling mica. Then, the mica is finely cleaved between its layers, and an interlayer cation such as a sodium ion and a lithium ion is dissolved in the solution. Accompanying this, the space between the layers of the mica is negatively charged, and the surface of the layers is positively charged. In this state, a sodium ion, which derives from sodium silicate, is electrically attracted to the negatively charged space between the layers of the mica. Then, the sodium ion intercalates between the layers and an intercalation compound of mica is formed. This compound is the main component of the liquid foaming material [0025] 21. When the liquid foaming material 21 is heated and condensed, it changes into a gel-like material. This gel-like material is applied to the outer surface of the conduit 20.
[0026] When the gelled foaming material [0026] 21 is heated further, the foaming material 21 foams and expands following the evaporation of water. The foaming material 21 hardens to a sufficient degree after several minutes. When hardened, the volume of the foaming material 21 is three to five times the volume of the foaming material 21 when in its gel form.
[0027] This expansion is based on the following process. The reduction of water from heating is accompanied by the approach of the layers of mica to one another. Since the space between the layers is negatively charged and the surface of the layers is positively charged, the ends of each layer is attracted to the surface of another layer. Then, a three-dimensional molecular structure, which is bulky and shaped like a house of cards, is formed. As the water vaporizes, many spaces are formed in the foaming material [0027] 21. In other words, the foaming material 21 expands by the formation of the spaces and by the formation of the house-of-cards structure. As the water evaporates further, the foaming material 21 solidifies. The heating of the foaming material 21 is preferably performed at 150 to 200 degrees Celsius and, if necessary, at higher temperatures.
[0028] The passage structure [0028] 19 uses a characteristic of the foaming material 21. That is, before the passage structure 19 is inserted in the through hole 13, the gelled foaming material 21 is applied to the outer surface of the conduit 20. Then, the conduit 20 is inserted in the through hole 13 as shown in FIG. 3. The foaming material 21 is surrounded by the inner surface of the through hole 13. Then, a heating apparatus such as a burner 29 is inserted inside the conduit 20, and the foaming material 21 is heated through the conduit 20. Thus, the volume of the foaming material 21 is increased. As a result, as shown in FIG. 4, the foaming material 21 seals the annular space between the inner surface of the through hole 13 and the conduit 20. Tens of minutes later, the foaming material 21 completely hardens and becomes a fireproof filler 23. In this way, the conduit 20 is firmly fixed in the through hole 13.
[0029] After the fireproof filler [0029] 23 is formed, a wire 22 is inserted in the conduit 20 as shown in FIG. 1. To seal the space between the inner surface of the conduit 20 and the wire 22, fireproof material 25 is injected to fill both ends of the conduit 20. Material like a chloroprene rubber that includes sodium silicate hydrate (water glass) is used for the fireproof material 25.
[0030] The fireproof filler [0030] 23 fills the space between the through hole 13 and the conduit 20, and the fireproof material 25 fills the space between the conduit 20 and the wire 22. As a result, if a fire occurs in a building in which the passage structure 19 is installed, the through hole 13 and the conduit 20 will not provide a passage for fire and smoke. This slows the speed of fire and smoke.
[0031] The first embodiment has the following advantages. The foaming material [0031] 21 foams rapidly when heated and hardens quickly. This improves efficiency and prevents the formation of space caused by the weight of the conduit 20 between the fireproof filler 23 and the conduit 20. As a result, there is no need to refill the hole with the foaming material 21. Further, cost of construction is lowered due to the increased efficiency.
[0032] The conduit [0032] 20 is made of metal. This ensures efficient transmission of heat to the foaming material 21 through the conduit 20 when the conduit 20 is heated from inside. As a result, the foaming material 21 foams efficiently and the space between the through hole 13 and the conduit 20 is fully sealed by the fireproof filler 23.
[0033] The fireproof material [0033] 25 fills the space between the wire and the inner surface at both ends of the conduit 20. If a fire occurs in a building in which the passage structure is installed, the spread of fire and smoke is impeded.
[0034] The foaming of the foaming material [0034] 21 completely seals the space between the inner surface of the through hole 13, annular grooves 18, and the conduit 20. After tens of minutes, the foaming material hardens and forms the fireproof filler 23. Therefore, only a small amount of the foaming material 21 is necessary to form the fireproof filler 23.
[0035] The foaming material [0035] 21 is an inorganic material and does not carbonize when heated. Thus it is heat-resistant. If there is a fire, the fireproof filler 23, which is made of the foaming material 21, does not carbonize and impedes fire.
[0036] The foaming material [0036] 21 foams substantially uniformly, which positions the conduit 20 in approximately the center of the through hole 13. This avoids the task of manually holding the conduit 20 in the center of the through hole 13.
[0037] The gelled foaming material [0037] 21 foams by evaporation of water from the material 21 when heated. In addition, since the foaming material 21 includes swelling mica and sodium silicate, it hardens.
[0038] In the passage structure [0038] 19, the foaming material 21 is applied to the outer surface of the conduit 20. This reduces the number of parts required and facilitates installation.
[0039] The foaming material [0039] 21 is applied to the outer surface of the conduit 20 in advance of placing the conduit 20 in the hole 13. Thus, there is no need to inject the foaming material 21 between the through hole 13 and the conduit 20.
[0040] The volume of the foaming material [0040] 21 becomes three to five times the original volume after heating, and the foaming material hardens in tens of minutes. As a result, the wire 22 can be inserted in the conduit 20 without significant delay.
[0041] The annular grooves [0041] 18 formed on the inner surface of the through hole 13 resist movement and dislodgment of the fireproof filler 23.
[0042] The surface of the conduit [0042] 20 is rough. This also increases the resistance of the fireproof filler 23 against movement.
[0043] Second Embodiment [0043]
[0044] A passage structure according to a second embodiment of the present invention will now be described concentrating on differences from the first embodiment. [0044]
[0045] Unlike the method described with respect to the first embodiment, the foaming material [0045] 21 is not applied to the outer surface of the conduit 20 prior to insertion of the tube 20. Instead, as shown in FIG. 5, after the conduit 20 is inserted in the through hole 13, gel or liquid-type foaming material 21 is forced, or injected, between the inner surface of the through hole 13 and the conduit 20 by a dispenser apparatus 26. As in the first embodiment, the foaming material 21 is heated through the conduit 20 from inside by the burner 29 so that it foams. Then, the foaming material 21 seals the space between the inner surface of the through hole 13 and the conduit 20. The foaming material 21 hardens in tens of minutes and forms the fireproof filler 23. As a result, the conduit 20 is fixed in the through hole 13.
[0046] The second embodiment has the following advantages in addition to those of the first embodiment. The foaming material [0046] 21 is injected or delivered after the conduit 20 is inserted in the through hole 13. This permits the quantity of the foaming material 21 to be adjusted in accordance with the size of the space between the through hole 13 and the conduit 20. Therefore, the fireproof filler 23 effectively seals the space between the through hole 13 and the conduit 20. This further prevents waste of the foaming material 21 and thus lowers costs.
[0047] Third Embodiment [0047]
[0048] A third embodiment will now be described concentrating on the differences from the other embodiments. [0048]
[0049] In the third embodiment shown in FIG. 6, two bands of foaming material [0049] 21 are applied to separate sections of the outer surface of the conduit 20. The outer ends of the bands of foaming material 21 are axially spaced from one another by a distance that is about the same as the thickness of the partition 12. Therefore, when the conduit 20 is inserted in the through hole 13, the two bands of foaming material 21 are located inside the through hole 13. When the two bands of foaming material 21 are heated, as in the first embodiment, each band of foaming material 21 expands and seals a respective end of the through hole 13. Annular grooves 18 are formed to surround the parts of the foaming material 21.
[0050] According to the third embodiment, the amount of the foaming material [0050] 21 is reduced, which reduces costs.
[0051] Fourth Embodiment [0051]
[0052] A forth embodiment will now be described concentrating on the differences from the other embodiments. [0052]
[0053] In the fourth embodiment, a thermal expansion material [0053] 27 containing soft rubber material is used instead of the inorganic foaming material 21. First, the thermal expansion material 27 is applied to the outer surface of the conduit 20 in a cylindrical band. The thermal expansion material 27 may be applied to the outer surface of the conduit 20 after the conduit 20 is inserted. In that case, a sheet of thermal expansion material 27 may be placed around the surface of the conduit 20.
[0054] As shown in FIGS. [0054] 7(a), (b), flanged retainers 28 are fixed to both ends of the conduit 20 by screws 30.
[0055] The conduit [0055] 20 with the applied thermal expansion material 27 is inserted in the through hole 13. Then, the two retainers 28 are respectively fixed to the conduit 20 by the screws 30. In this way, the conduit 20 is fixed in the partition 12 (See FIG. 7 (a)). When the conduit 20 and the retainers 28 are heated, the thermal expansion material 27 expands and forms the fireproof filler 23. In this way, the space between the inner surface of the through hole 13 and the conduit 20 is sealed. After cooling, the wire 22 is inserted in the conduit 20 (see FIG. 7 (b)). The conduit 20 is fixed to the partition 12 by the thermal expansion material 27 and the retainers 28.
[0056] It is obvious to those skilled in the art that the first through the fourth embodiments may be varied as follows, and the following is within the spirit of the present invention. [0056]
[0057] In the second embodiment, the foaming material [0057] 21 may be applied to the inner surface of the through hole 13. In this case, the foaming material 21 is directly heated.
[0058] In the first through fourth embodiments, the metal rings [0058] 15 on the outer surface of the void pipe 14 may be omitted.
[0059] In the first through fourth embodiments, the foaming material [0059] 21 may be directly heated.
[0060] In the first through third embodiments, a cylindrical sheet of foaming material [0060] 21 may be placed on the outer surface of the conduit 20.
[0061] In the first through the fourth embodiments, a material like foam concrete, which expands and hardens by chemical reaction, may be used. For example, portland cement, quick lime (calcium oxide CaO), silica rock, water, aluminum, foam stabilizer, and iron cuttings are mixed. The resulting slurry is delivered between the outer surface of the conduit [0061] 20 and the through hole 13.
[0062] In the slurry, calcium hydroxide is generated by the hydration of CaO and by the hydration of 3CaO·SiO[0062] 2, 2CaO·SiO2 in the portland cement. Further, hydrogen gas (H2) is generated by the reaction of quick lime, aluminum and water, or by the reaction of aluminum and water. This forms foam in the slurry. Accordingly, the slurry expands to a predetermined volume. Colloidal glue (3CaO·2SiO2·3H2O), which is generated by the hydration 3CaO·SiO2, 2CaO·SiO2 in the portland cement at the same time with the foaming, hardens the slurry. In this way, cellular concrete is formed, which seals the space between the outer surface of the conduit 20 and the through hole 13. As a result, the conduit 20 is firmly supported in the partition 12.
[0063] In the first through the third embodiments, the retainers [0063] 28 of the fourth embodiment may be used. In this case, the conduit 20 is more firmly attached to the partition 12.
[0064] In the first through the fourth embodiments, the shape of the conduit [0064] 20 is not limited to a cylindrical conduit. The cross-sectional shape of the conduit 20 may be square or triangular or otherwise polygonal.
[0065] In the first through the fourth embodiments, the object inserted in the conduit [0065] 20 is not limited to the wire 22. For example, a gas pipe or a water pipe may pass through the conduit 20.
[0066] It should be apparent to those skilled in the art that the present invention may be embodied in many other specific forms without departing from the spirit or scope of the invention. Therefore, the present examples and embodiments are to be considered as illustrative and not restrictive and the invention is not to be limited to the details given herein, but may be modified within the scope and equivalence of the appended claims. [0066]
权利要求:
Claims (25)
[1" id="US-20010001355-A1-CLM-00001] 1. A passage structure for permitting an object to pass through a partition, wherein a through hole is formed in the partition, the passage structure comprising:
a conduit located inside the through hole; and
a foaming material for filling a space between the outer surface of the conduit and the inner surface of the through hole by expansion, wherein the foaming material is expanded after the conduit is located in the through hole and the foaming material, after expanding, seals the space between the inner surface of the through hole and the outer surface of the conduit.
[2" id="US-20010001355-A1-CLM-00002] 2. The passage structure according to
claim 1 , wherein the foaming material hardens after it expands.
[3" id="US-20010001355-A1-CLM-00003] 3. The passage structure according to
claim 2 , wherein the foaming material is fire-resistant after it expands.
[4" id="US-20010001355-A1-CLM-00004] 4. The passage structure according to
claim 2 , wherein the conduit is made of metal.
[5" id="US-20010001355-A1-CLM-00005] 5. The passage structure according to
claim 2 , wherein the conduit has a rough outer surface where the foaming material contacts the conduit.
[6" id="US-20010001355-A1-CLM-00006] 6. The passage structure according to
claim 2 , wherein the foaming material expands when heated.
[7" id="US-20010001355-A1-CLM-00007] 7. The passage structure according to
claim 2 , wherein the foaming material expands as a result of a chemical reaction.
[8" id="US-20010001355-A1-CLM-00008] 8. The passage structure according to
claim 2 , wherein the foaming material includes an inorganic compound.
[9" id="US-20010001355-A1-CLM-00009] 9. The passage structure according to
claim 8 , wherein the foaming material contains swelling mica, which is dispersed in a alkaline salt solution, as a principal ingredient.
[10" id="US-20010001355-A1-CLM-00010] 10. The passage structure according to
claim 2 further including a heat-resistant material located near the ends of the inner surface of the conduit, wherein the heat-resistant material seals a space between the outer surface of an object located within the conduit and the inner surface of the conduit at the ends of the conduit.
[11" id="US-20010001355-A1-CLM-00011] 11. The passage structure according to
claim 1 further including a pair of retainers for connecting the conduit to the partition, wherein the retainers are respectively attached to the conduit on opposite sides of the partition.
[12" id="US-20010001355-A1-CLM-00012] 12. The passage structure according to
claim 1 , wherein the foaming material is a coating that is applied to the conduit prior to installation of the passage structure.
[13" id="US-20010001355-A1-CLM-00013] 13. A conduit for permitting an object to pass through a partition, wherein a through hole is formed in the partition, the conduit comprising:
an expandable foaming material that expands by a predetermined operation, wherein the foaming material is located on at least a portion of the outer surface of the conduit.
[14" id="US-20010001355-A1-CLM-00014] 14. The conduit according to
claim 13 , wherein the foaming material hardens after it expands.
[15" id="US-20010001355-A1-CLM-00015] 15. The conduit according to
claim 14 , wherein the foaming material is fire-resistant after it expands.
[16" id="US-20010001355-A1-CLM-00016] 16. The conduit according to
claim 13 , wherein the conduit is made of metal.
[17" id="US-20010001355-A1-CLM-00017] 17. The conduit according to
claim 13 , wherein the conduit has a rough outer surface where the foaming material contacts the conduit.
[18" id="US-20010001355-A1-CLM-00018] 18. The conduit according to
claim 13 , wherein the foaming material expands when heated.
[19" id="US-20010001355-A1-CLM-00019] 19. The conduit according to
claim 13 , wherein the foaming material expands as a result of a chemical reaction.
[20" id="US-20010001355-A1-CLM-00020] 20. The conduit according to
claim 13 , wherein an object is inserted into the conduit after the foaming material expands.
[21" id="US-20010001355-A1-CLM-00021] 21. A method for sealing a space between an inner surface of a through hole and an outer surface of a conduit, wherein the through hole is formed in a partition, the seal method including:
inserting the conduit into the through hole;
locating a foaming material between the inner surface of the through hole and the outer surface of the conduit; and
expanding the foaming material by stimulating a reaction in the foaming material.
[22" id="US-20010001355-A1-CLM-00022] 22. The method according to
claim 21 further including hardening the foaming material after the expansion.
[23" id="US-20010001355-A1-CLM-00023] 23. The method according to
claim 22 , wherein an object is inserted into the conduit after the hardening.
[24" id="US-20010001355-A1-CLM-00024] 24. The method according to
claim 23 further including sealing a space between the outer surface of the object and the inner surface of the conduit at the ends of the conduit.
[25" id="US-20010001355-A1-CLM-00025] 25. The method according to
claim 21 , wherein the expanding step includes heating the foaming material.
类似技术:
公开号 | 公开日 | 专利标题
US6530187B2|2003-03-11|Partition passage and method of installing
US6390135B1|2002-05-21|Conduit assembly and method of installation
US4901488A|1990-02-20|Fire/smoke protection structure for a plastic pipe or cable channel portion in a floor or wall
US4424867A|1984-01-10|Heat hardening sealant-gel for flexible couplings
US4363199A|1982-12-14|Fire resistant sealing system for holes in fire resistant building partitions
EP1714364B1|2007-08-29|System and method for sealing an opening in a wall in which at least one transport device such as a cable, conduit or tube has been fed through
JP4443521B2|2010-03-31|Fire prevention parts
AU2012281945A1|2014-01-16|Fire-resistant reinforcement structure, fire-resistant reinforcement architectural member, fire-resistant reinforcement method for architectural member
WO1988005804A1|1988-08-11|Fire-resistant composition
JP4287384B2|2009-07-01|Penetration closure
JPH1119242A|1999-01-26|Fireproof pipe of block piercing part, fireproof structure of block piercing part and fireproof construction method for block piercing part
EP0045216B1|1984-09-05|Cavity wall insulation
RU2189521C2|2002-09-20|Method of pipe heat insulation and waterproofing
JPH087779Y2|1996-03-04|Fireproof structure for penetration of building fireproof slab
JP2955446B2|1999-10-04|Fire prevention treatment method and fire prevention equipment for pipe penetration
JP2001252367A|2001-09-18|Dividing wall penetration duct and method of using the same
JPH07259211A|1995-10-09|Blocking type fire-proof construction and its work method
JPH0595133U|1993-12-24|Fireproof structure of the penetration part of the heat insulation cladding in the fireproof compartment
JP3836297B2|2006-10-25|Penetration cylinder for fire protection compartment and its fixing method to fire protection compartment
JP2018109283A|2018-07-12|Sleeve, compartment penetration structure, and refractory filling structure
KR920000202Y1|1992-01-15|Installation structure of cable tube
JPH084952A|1996-01-12|Fireproof structure of through part of refractory slab for building and construction thereof
JPH05276635A|1993-10-22|Fire prevention construction at through-hole portion of fire-resistant slab of building
JPH0882390A|1996-03-26|Embedding refrigerant pipe unit
EP0759961A1|1997-03-05|Intumescent compositions
同族专利:
公开号 | 公开日
TW508419B|2002-11-01|
FR2777627A1|1999-10-22|
JP3683727B2|2005-08-17|
DE19917127B4|2004-05-06|
DE19917127A1|1999-10-21|
FR2777627B1|2004-06-04|
US6530187B2|2003-03-11|
KR19990082762A|1999-11-25|
JP2000000326A|2000-01-07|
引用文献:
公开号 | 申请日 | 公开日 | 申请人 | 专利标题
WO2005046016A1|2003-11-07|2005-05-19|Georg Wichmann|Fire-prevention device, assembly for installing a fire-prevention device, method for producing said assembly and fire-prevention cable duct|
US20070074808A1|2005-04-26|2007-04-05|L&L Products, Inc.|Member for baffling, reinforcement or sealing|
US20070283644A1|2006-04-19|2007-12-13|Marco Fischer|Leadthrough for a conduit|
US20090320392A1|2006-07-25|2009-12-31|Deutsche Rockwool Mineralwoll Gmbh & Co. Ohg|Wall leadthrough for leading a line through a building wall|
US20110018206A1|2007-06-22|2011-01-27|Beele Engineering B.V.|Method and sealing system for sealing an annular space between a rigid conduit and a pipe, tube or duct extending through the conduit and made of a thermally weakenable material|
US8381403B2|2005-05-25|2013-02-26|Zephyros, Inc.|Baffle for an automotive vehicle and method of use therefor|
US20140020315A1|2012-07-23|2014-01-23|Hilti Aktiengesellschaft|Assembly for a line conduit|
ES2572150A1|2014-11-28|2016-05-30|Univ Valladolid|Procedure and device against the air permeability of pipes with wiring |
WO2017091371A1|2015-11-25|2017-06-01|3M Innovative Properties Company|Firestop system for marine or off-shore applications|
CN107202202A|2017-06-29|2017-09-26|广船国际有限公司|A kind of freezer bulkhead cable sealing assembly|
US20190305539A1|2015-09-29|2019-10-03|Hilti Aktiengesellschaft|Line feedthrough for feeding lines through a component|DE285393C|1914-01-01||||
FR2485677B1|1980-06-27|1985-09-20|Poujaud Edouard|FLEXIBLE AND ELASTIC PRODUCT FOR MAKING PROTECTIVE SEALS AND TRIMS|
DE8034605U1|1980-12-24|1981-06-19|Ellrott, Egon, 2800 Bremen|DEVICE FOR THE INTRODUCTION OF INSTALLATION PIPES AND CABLES IN A BASEMENT BUILDING|
US4424867A|1981-03-31|1984-01-10|Fiberglas Canada Inc.|Heat hardening sealant-gel for flexible couplings|
US4607469A|1984-01-03|1986-08-26|Team, Inc.|Seal for water proofing a utility line conduit and a method of forming the seal|
NL8601145A|1986-05-05|1987-12-01|Filoform Chem Ind Bv|METHOD AND APPARATUS FOR WATERPROOF SEALING OF A CABLE AND / OR PIPE TRANSIT OPERATION IN A WALL OR THE LIKE, USING A FOAMABLE RESIN|
DE3804927A1|1988-02-17|1989-08-31|Rxs Schrumpftech Garnituren|Tubular device for leading-through elongate objects, and process for producing such a device|
DE3821969C1|1988-06-29|1990-02-01|Michael Dr. 8000 Muenchen De Spaeth||
US4848043A|1988-09-14|1989-07-18|Harbeke Gerold J|Under floor fire stop coupling and method|
DE3918892C1|1989-06-09|1990-11-29|Schaum-Chemie Wilhelm Bauer Gmbh & Co Kg, 4300 Essen, De|Fire-resistant closure in wall - fits closely round pips and cables and incorporates inorganic foam layer|
DE4008032A1|1990-03-14|1991-09-19|Helmut Stoeger|Cable wall guide hole - has foam insert of porous material located around cable|
US5174077A|1990-04-24|1992-12-29|The Furukawa Electric Co., Ltd.|Fire protecting structure of channel portion of plastic piping in a fire partition|
DE4109614C2|1991-03-23|2000-11-02|Multica Verpackungen Gmbh|House entry for supply lines, especially for gas lines|
US5347767A|1992-01-29|1994-09-20|Rudolf Roth|Fire retardant sleeve|
DE4234374A1|1992-10-12|1994-04-14|Mueller Michaela|Fireproof material for sealing cable ducts in walls etc. - comprises 2-component polyurethane compsn. with intumescent additives, which produces a sec. protective foam in case of fire.|
US5351448A|1993-04-19|1994-10-04|Balco, Inc.|Fire barrier|
US5456050A|1993-12-09|1995-10-10|Construction Consultants & Contractors, Inc.|System to prevent spread of fire and smoke through wall-breaching utility holes|
US5548934A|1994-09-06|1996-08-27|Minnesota Mining And Manufacturing Company|Firestop apparatus for allowing pipe movement|
DE29600856U1|1996-01-19|1996-03-07|Promat Gmbh|Pipe insulation through wall or ceiling|DE19955763B4|1999-11-19|2004-04-29|Hilti Ag|Method for sealing a gap between a bushing present in a component and at least one object projecting through the bushing, and sealing therefor|
DE10150075A1|2001-10-10|2003-04-17|Roxtec Ingenieur Gmbh|Module for a sealed passage for cables/pipes, through constructions, has a lateral recess around its outer sealing surfaces with at least one drilling to the interior to test the hermetic sealing|
US7045479B2|2003-07-14|2006-05-16|Headwaters Nanokinetix, Inc.|Intermediate precursor compositions used to make supported catalysts having a controlled coordination structure and methods for preparing such compositions|
US6810568B1|2003-07-14|2004-11-02|Marvin Lacoste|Refrigerant copper line protector and method of repairing|
US20060070319A1|2004-10-01|2006-04-06|Flynn Matthew J|Devices and systems for preventing the propagation of fire along cables and methods of preventing same|
DE102005007948B4|2005-02-22|2007-01-18|Warema Renkhoff Gmbh|Thermally insulated feedthrough for movable drive elements through external building envelopes and method for their production|
US8051614B1|2005-06-21|2011-11-08|Sprint Communications Company L.P.|Intumescent structure for ducting carrying communications cabling|
US20070152440A1|2005-12-30|2007-07-05|Keyes Thomas J|Pipe sealing system|
US20080022612A1|2006-07-31|2008-01-31|Jones Thomas P|Apparatus for maintaining the structural integrity of a pipe passing through a building partition|
DE102006035474B4|2006-12-01|2008-12-11|Hilti Aktiengesellschaft|Cable bushing|
DE102011004646A1|2011-02-24|2012-08-30|Robert Bosch Gmbh|Wiper blade for cleaning windows, especially of motor vehicles|
EP2554886A3|2011-08-03|2017-10-11|HILTI Aktiengesellschaft|Use of a passive fire alarm system for conduits and corresponding method.|
DE102011082911A1|2011-09-19|2013-03-21|Hilti Aktiengesellschaft|Fire protection element|
JP5996522B2|2013-12-25|2016-09-21|エスペック株式会社|Wiring attachment device for box-shaped device|
FR3017920B1|2014-02-24|2016-09-30|Grtgaz|SHUTTER FOR OPENING A SAIL|
JP6533404B2|2015-03-27|2019-06-19|積水化学工業株式会社|Fire protection device and fire protection structure of building|
CN107466243B|2015-04-17|2021-06-04|3M创新有限公司|Penetration fire-retardant system|
CN107532751A|2015-04-17|2018-01-02|3M创新有限公司|Smog and sound barriers for building penetration portion|
US11165231B2|2016-04-25|2021-11-02|Glenn Liubakka|Apparatus for different sized boxes|
US10840683B1|2016-04-25|2020-11-17|Northeast Entrepreneur Fund, Inc.|Electrical conduit coupling system|
CN105790183B|2016-05-05|2018-02-13|温州圆立电力科技有限公司|Cable cavern high temperature resistant waterproof plugging device|
JP6388022B2|2016-12-27|2018-09-12|積水ハウス株式会社|Penetration fireproof member and fireproof construction|
KR102016345B1|2018-12-21|2019-08-30|선진피앤에프|Structure module for diffusion prevention of flame and harmful gas using expandable sleeve|
法律状态:
1999-04-02| AS| Assignment|Owner name: MIRAI INDUSTRY CO., LTD., JAPAN Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:SHIMIZU, SHOHACHI;REEL/FRAME:009887/0150 Effective date: 19990323 |
2006-05-17| FPAY| Fee payment|Year of fee payment: 4 |
2010-10-18| REMI| Maintenance fee reminder mailed|
2011-03-11| LAPS| Lapse for failure to pay maintenance fees|
2011-04-11| STCH| Information on status: patent discontinuation|Free format text: PATENT EXPIRED DUE TO NONPAYMENT OF MAINTENANCE FEES UNDER 37 CFR 1.362 |
2011-05-03| FP| Expired due to failure to pay maintenance fee|Effective date: 20110311 |
优先权:
申请号 | 申请日 | 专利标题
JP10-124076||1998-04-17||
JP12407698||1998-04-17||
JP01182399A|JP3683727B2|1998-04-17|1999-01-20|How to close the penetration|
JP11-011823||1999-01-20||
[返回顶部]