专利摘要:
The procedure to isolate the damaged section in electrical lines of the 3rd category, consists of the use of an adapted dielectric strength meter, in two versions: - Mobile version (RDM): It is characterized by the connection of the device with insulated poles to the damaged line, without voltage, and governed by remote control. - Fixed version (RDF): It is characterized by the control and command of the device with GPRS technology, located inside an MV line cell. When the line is faulty, without voltage, with the trial-error method, the dielectric strength of the different sections of the line is tested until the damaged section is located. Once the section where the fault is identified, it is isolated by sectioning it, and the power supply is restored to the rest of the line. (Machine-translation by Google Translate, not legally binding)
公开号:ES2719933A1
申请号:ES201800265
申请日:2018-11-23
公开日:2019-07-16
发明作者:De Heredia Escolano David Fernandez
申请人:De Heredia Escolano David Fernandez;
IPC主号:
专利说明:

[0001]
[0002] Procedure to isolate the damaged section using adapted dielectric strength meter, in 3rd category distribution networks.
[0003]
[0004] Technical sector
[0005]
[0006] The present invention is applicable to electricity distribution networks of Category 3 , or Medium Voltage (hereinafter MV lines), used by distribution companies to serve the electricity market. The nominal voltage lines are equal to or greater than 1 KV and less than 30 KV.
[0007]
[0008] Background of the invention
[0009]
[0010] Electric power is essential for the functioning of modern societies, so that one way to measure the development of a country is the amount of energy it consumes. Electrical infrastructures are increasingly complex and difficult to control, and a higher quality of energy supply is required, respecting the environment, and prioritizing the physical integrity of the people involved in the operation of the facilities and society in general.
[0011]
[0012] I am going to limit this description to the distribution of electric power of MV lines, competition of the distribution companies, which start at the Electrical Substations that transform the transport voltage into High Voltage to Medium Voltage, and end at the Medium Transformation Centers Low Voltage Tension.
[0013]
[0014] The supply of electricity offered by the distribution companies to the commercialization companies must meet quality requirements. This quality is standardized by rules that set parameters, voltage levels, sine waveform, harmonic distortion levels, supply interruptions, etc. Electricity is a consumer good and must maintain a certain quality, so that it can be used by all the equipment that depends on it, directly or indirectly.
[0015]
[0016] The most important defect that can occur in the quality of the electricity supply is surely the interruption of the supply. The ideal situation would be that there were no power outages 24 hours a day, 365 days a year, but this is difficult to accomplish for various reasons. Sometimes it is necessary to cut off the supply on a scheduled basis to do maintenance work on the facilities, to connect new installations, etc., and other times, it is unforeseen, a fault occurs at some point in the network for multiple reasons, ( adverse weather conditions, such as rain, hail, floods, snow, storms, wind, etc .; impact of external elements such as animals, birds, trees, foreign bodies; third-party activities such as excavators, fires, people, vandalism, vehicles, theft; material degradation; maneuver, assembly errors, etc.).
[0017]
[0018] When a MT line breaks down, the protection relay of that line acts, ordering the opening of the circuit breaker (INT. A, according to FIG. 1), located in the electrical substation that supplies it (SET, according to FIG. 1) . If there is a recloser, it sends a closing order to the circuit breaker and if the fault persists, the protection relay immediately orders the switch to be opened immediately, in order to minimize the damage that the fault may cause in the whole of the installations, and its possible impact on people, animals or things. The defective section must be isolated as quickly as possible, to restore service to other consumers.
[0019] In developed countries, all distribution companies have an Energy Control Center, where there are operators who control the state of the network in real time at all times. Virtually all substations are telecontrolled (SET according to FIG. 1), and this means that when a MT line breaks down, and the circuit breaker in the SET opens, the operator of the control center sees it, and starts the procedure established to delimit and isolate the damaged section, and restore the electricity supply to the rest of the facilities. This procedure is based on the trial-error method.
[0020]
[0021] The configuration of the Medium Voltage lines is very varied, but could be summarized in three:
[0022]
[0023] a) Ring distribution, characteristic of urban areas, in which the lines and transformation centers form a ring that closes in at least two positions of the same substation. In most of the transformation centers, the line enters from the previous transformation center and leaves towards the subsequent transformation center. In these transformation centers (in FIG. 1 they are represented by rectangles with the designation CT__), in addition to having Medium Voltage to Low Voltage transformers, there are switch-disconnectors that can open the ring in both directions.
[0024]
[0025] b) Radial distribution, characteristic of rural areas, in which the Medium Voltage lines start from a position of the High Voltage / High Voltage electrical substation, with its circuit breaker, and supply electrical power to the transformer centers connected to the same. There is no possibility to feed this line from another substation position.
[0026]
[0027] c) Mixed distribution, which would include parts of the previous two.
[0028]
[0029] Continuing with the aforementioned trial-error method, when a line is opened by tripping a protection, and after a re-coupling of it automatically, or, a switch closure test performed by the operator of the control center, the line triggers again, it is considered that there is a permanent breakdown in it. It is common that in the MT lines there is some transformation center (hereinafter CT), or telecontrolled sectioning (in FIG. 1 they are represented by a black rectangle). The next step to be followed by the operator of the control center is to section parts of the line, opening switches-disconnectors remotely located inside telecontrolled CTs. Each time a part of the line is sectioned, the operator closes the SET circuit breaker. If the circuit breaker remains closed it means that the fault is in the open line. If the circuit breaker reopens in order of protection, it means that the fault is "upstream" of the switch-disconnector open by remote control, that is, between the SET and the switch-disconnector open. This operation is applicable to the centers of transformation or remote controlled disconnectors On the rest of the installations, the opening and closing maneuvers must be done manually, by duly trained and equipped field operators, always under the orders of the operator of the control center.
[0030]
[0031] I have already referred several times to FIG. 1. It is an example of a Medium Voltage distribution scheme, of the wide casuistry that exists in the distribution companies. It simulates a fault in the branch to the CTF4 transformation center, in which one of the phases has lost its insulation and is in contact with earth. To know the behavior of the network in the event of a fault, the type of neutral connection of the AT / MT transformer in the SET is essential. Basically there are three ways to connect the neutral:
[0032] - Neutral directly connected to ground, characterized by high short circuit intensities.
[0033] - Isolated neutral, with very low short circuit intensities but high overvoltages in case of breakdown.
[0034]
[0035] - Neutral with impedance, which depending on it, would behave in the event of a breakdown with intermediate intensity and voltage values to the two previous extreme cases.
[0036]
[0037] If in the case of FIG. 1 we have the neutral directly connected to ground, most likely it blows the F4 fuse (the black dots represent sectioning with fuses). The circuit breaker of line A has tripped (INT.A), has blown the fuse F4 clearing the fault and when closing the switch, either automatically or manually, the supply is restored to all consumers except those that are feed from CTF4. We have considered that the ring formed by lines A and B is open in CTB15.
[0038]
[0039] In the event that the SET transformer is with the neutral isolated, since the homopolar currents are very small, it is most likely that the F4 fuses do not blow. What is appropriate is to do all the necessary tests, opening and closing sectionings, until detecting the damaged section (referral to CTF4, a priori unknown). This is the trial-error method. It is necessary to determine what criteria are used to establish priorities in the maneuver of the different sections, as there are many variables to take into account: older parts of the line and therefore with greater probability of breakdown, areas with greater installed power to which it is of interest minimize the time without supply, special consumers, number of desirable tests to be carried out, and therefore number of errors, which means shots or "blackouts" to consumers of the entire damaged line (line A), time to isolate the fault, which is sometimes in compromise with the number of shots, as local operators have to travel considerable distances, with geographical obstacles such as rivers, highways, farms and roads flooded by rain, etc.
[0040]
[0041] If we consider the criterion of achieving the minimum number of shots or blackouts to all consumers of line A, when firing the INT. In order of protection, the logical sequence would be as follows: Open by remote control switch-disconnector output to C in CTC1, close INT. A by remote control, open D (small black squares represent disconnectors without fuses), open E, open H, open F, close switch-disconnector output to C in CTC1 by remote control, close F, INT.A trip in SET, open F (fault is in this section), close INT. A, close H, close D, close E, open F1, open F2, open F4, open F5, open F3, close F, close F1, close F2, close F4, INT shot. A, open F4 (fault located in this section), close INT.A, close F3, close F5. At this moment everything is already in service except for the F4 branch, which must be traversed, find the faulty point, repair it and close F4 again. We observe that in each sectioning that is maneuvered, it is necessary to go twice, which lengthens the time considerably.
[0042]
[0043] If we consider the criterion of locating the damaged section in the fastest way, the logical sequence will be as follows: INT shot. A, open switch-disconnector output to C in CTC1, close INT.A, open D, close switch-disconnector in CTC1, trip INT. A (the fault is not in branch D), open switch-disconnector in CTC1, close INT.A, close D, open E, close switch-disconnector in CTC1, trip INT.A, open switch-disconnector in CTC1, close INT .A, close E, open F, close switch-disconnector in CTC1 (does not trip INT.A, then the fault is in branch F), open F1, close F, trip INT.A, open F, close INT.A, close F1, open F2, close F, trip INT.A, open F, close INT.A, close F2, open F4, close F, (Do not fire INT.A, then the fault is in branch F4). In this way you only have to go to each section once, but the number of shots, that is blackouts, on line A is very high.
[0044]
[0045] Between these two extreme criteria there are many intermediate options, which will depend on many variables already described.
[0046] Risks and disadvantages of this procedure to isolate the damaged section
[0047]
[0048] The procedure described to isolate the damaged section has risks and disadvantages, such as those mentioned below:
[0049]
[0050] a) The high short-circuit intensities that occur in a fault, in the case of AT / MT transformers with neutral to ground, and to a lesser extent with neutral with impedance, can aggravate the damaged point with each test and trip that occurs. But they not only aggravate the damage caused by the shots, but also affects healthy equipment and elements of the damaged circuit, causing premature aging of the same. This is the case of existing joints, terminals, connections, disconnectors and other more sensitive points. Special attention deserves the automatic switch of the SET that clears the fault with each test, and the AT / MT transformer also of the SET, which supports overheating in its windings and electrodynamic overexertion. The short-circuit currents depend on many variables: SET transformer power, fault point distance, circuit section of the faulty circuit, fault resistance, etc. But its magnitude can be thousands of amps.
[0051]
[0052] b) The overvoltages that support the healthy phases when there is a single-phase earth fault (they represent approximately 80% of the faults), which also depends on the neutral connection of the SET transformer. In the case of isolated neutral, they can be of the order of 1.8 times the nominal voltage of the line. These surges also negatively affect all the elements of the faulty circuit of the distribution company, shortening its life. But not only does it affect the installation of the distribution company, it also affects all the appliances and machinery of consumers who suffer the shots. Obviously, the more shots occur in the attempt to isolate the damaged section, the greater the damage.
[0053]
[0054] c) The number of shots that occur in the resolution of a fault affects the quality of supply of all consumers of the broken line. Although the duration of each shot and the closing of INT.A (FIG. 1) consequently is relatively small (the time it takes to undo the last maneuver), it is undoubtedly damaging the domestic consumer, and even more to businesses and companies , because they interrupt their production processes, computer data is lost, etc. For this reason and those described in sections a and b, it could be reasoned that the number of shots suffered by each consumer is included in the qualification of the quality of supply, and therefore, in the system of bonuses and penalties of the electric bill .
[0055]
[0056] d) The maneuvers in the field are done manually by operators properly trained and equipped, always under the orders of the energy control center, and are highly safe for their physical integrity. But zero risk does not exist. When large amounts of energy are handled, with high voltages and intensities, especially if there is a breakdown in the line, there is a certain risk. The equipment that is maneuvered can be broken creating a risk for the operator. Or there may be a breakdown in the same equipment that is being operated, also involving a risk. There is always the possibility of opening the nearest telecontrolled switch-disconnector before making a maneuver, but this means giving a blackout to the affected consumers.
[0057]
[0058] e) All maneuvers performed by field operators must be ordered by the control center. The general means of communication between the two is the mobile phone. This communication process consumes a time that is sometimes delayed due to various causes: coverage failures, coincidence of several failures and saturation of the control center operators, etc.
[0059] f) When a fault appears, a priori it is unknown what type it can be. There are especially dangerous for people, animals and things. When the cause is a protected person or species (even unprotected), every time the SET circuit breaker is closed, the situation can be significantly aggravated. The case of the broken cable that falls to the ground deserves special attention. With each test that is performed, the probability of causing a fire in certain circumstances, or that someone can contact it, increases.
[0060]
[0061] Explanation of the invention.
[0062]
[0063] The fundamental idea of this invention is to change the procedure to locate and isolate the damaged section, when a fault occurs in a Medium Voltage line. Instead of using the electricity itself that is distributed for use by consumers, I propose the use of a dielectric strength meter based on the many that exist in the market, but adapted to this new need.
[0064]
[0065] The fundamental technical characteristics of this meter are an adjustable output voltage of up to 30 KV and a test current of the order of a few tens of mA. The type of signal will be of Continuous Current (DC), and also of Alternating Current (AC), of sinusoidal form and of a frequency of the order of 0.05 Hz, with which we will be able to test distances of several tens of km. We will use it in CC mode for cases of single-phase faults, that is, insulation failure between a phase and ground; two-phase earth faults, and three-phase earth faults. These three types of fault represent more than 90% of the failures, the first being the most important with 80% of the cases. The maximum test voltage (between phase and ground), in these cases will be the simple line voltage, that is, the nominal voltage divided by 1.73.
[0066]
[0067] Vo = Vn / V3.
[0068]
[0069] For the other two types of fault, two-phase and three-phase isolated from earth, we will use the AC mode, testing between phases. The maximum test voltage will be the nominal voltage of the Vn line. In these cases, the QC test would not be valid, since most likely there are transformation centers fed from the line, and the primary windings of the transformers would lead us to miscalculation.
[0070]
[0071] To apply this new procedure, two versions of dielectric strength meter are proposed:
[0072]
[0073] a) MOBILE VERSION (hereinafter RDM):
[0074]
[0075] This device will be transportable in the vehicle used by the field operators. Based on the dielectric strength meters on the market, we will make several modifications for this new use, (these modifications can already be provided by the current state of the art):
[0076]
[0077] - The control and command will not be carried out from the same device, but will be operated by remote control. In this way, the physical integrity of the operator who manages it is ensured, in the event of high voltages that may unexpectedly appear on the MT line, such as the impact of lightning, the uncontrolled connection of a generator set, of a plant generator, etc.
[0078]
[0079] - It will be placed in a strategic point of the line, either in a support, or in a transformation center, with the use of insulating poles, in the same way that a set of portable lands is placed when a work is going to be done in a line of MT in discharge. The device will have two aluminum cables lined with 10 meters each, so that You can install on a normal MT stand. The section of the same will be small (of the order of 10 mm2 to 20 mm2), because they must withstand low intensities. It will also have a strap to attach it to the support.
[0080]
[0081] When a fault appears, once all the Voltage Sources are open, the control center delivers the installation that is without voltage, to the head of the field team responsible for solving the fault. It gives you the installation in Verification and Testing Regime. The work team verifies the absence of tension of the three phases with the corresponding pole. Once it is verified that there is no voltage in any phase, each of the phases with respect to earth is tested with the RDM, until the faulty phase is located. The RDM will record the lack of insulation with a test voltage lower than the simple line voltage, and in most cases with a test voltage much lower than the simple voltage. Once the faulty phase is located, the trial-error method already explained above will be used. The different sections will be opened, making a test with the RDM with each opening maneuver of each section, and thus the healthy sections are discarded, until the damaged section is identified. Once the damaged section has been isolated, which can no longer be sectioned, the work manager returns to the control center the installation that was in the Verification and Testing Regime, after disconnecting the RDM, and at this moment it can already be restore service to the entire line except for the broken section.
[0082]
[0083] In the unlikely event that the fault is of the two-phase or three-phase type isolated from earth, the test should be carried out by connecting the RDM cables to the faulty phases, and injecting the AC signal instead of the DC signal.
[0084]
[0085] In FIG. 2 an example of RDM installation on a support is observed. To perform these tests it is not necessary to section the centers of transformation of generating plants, because in no case, no operator will come into contact with the MT line. In the very unlikely event that electric power was injected into the MT line accidentally, the worst that could happen is a failure of the RDM.
[0086]
[0087] b) FIXED VERSION (hereinafter RDF):
[0088]
[0089] In this case, the RDF will be permanently connected in an MT line cell. This MT cell will in turn be connected to the cells of a telecontrolled transformation center. In FIG. 3 and 4 you can see an example. The control and control of the RDF can be done from the MT cell itself, or even from any geographical point where there is mobile phone coverage, using GPRS technology or higher. The current state of the art solves this option.
[0090]
[0091] The operation when a fault appears will be similar to that described for the mobile version, using the trial-error method, but in this case there is some variant. The RDF will have four wired connections, one for each phase and one for the earth. The cell in which the RDF is installed will have capacitive voltage detectors in the part of the bar. In addition there will be an electrical interlocking so that if voltage is detected in bars, the switch-disconnector of the RDF cannot be closed. The device itself can be configured to automatically discriminate the fault phase. The operator of the control center can govern all the transformation centers and telecontrolled sectioning, and can also control the RDF, therefore, and autonomously, can perform all the tests that the line allows by remote control. Even all these maneuvers could be automated in such a way that the operation of the control center operator was not required. When the operator of the control center can no longer carry out further tests at a distance, he may deliver the rest of the line without service to the head of works, under the Verification and Testing Regime, in order to continue doing the field maneuvers of the centers of transformation and disconnectors that are not telecontrolled, by the field operators.
[0092]
[0093] In FIG. 5 We can observe possible strategic locations of the meter, inside a transformation center if it is fixed, or in a support if it is mobile.
[0094]
[0095] Of the two criteria explained above regarding the sequence of the maneuvers (pages 5 and 6), we will use the one that manages to locate and isolate the damaged section in the fastest way, because with this procedure consumers will only suffer a cut of Supply: when the fault appears.
[0096]
[0097] We can always assess a mixed solution between the current and the proposed procedure (with risks and inconveniences already explained). In the case of FIG. 5, the current procedure can be continued until service is restored before the telecontrolled CTC1. From this moment on, the procedure object of this invention can be applied.
[0098]
[0099] Advantages of the invention
[0100]
[0101] a) With this procedure we use in the tests small intensities: 10, 20, 30 mA.
[0102] In this way, all possible damages that may arise when using the current intensities of up to several thousand amps disappear.
[0103]
[0104] b) The maximum voltages that we are going to inject with the meter will be the simple voltage for the phase-to-earth case, and the nominal voltage for the unlikely phase-phase case. In no case will surges appear, with the risk already mentioned that this implies.
[0105]
[0106] c) When a fault appears, the protection relay gives the opening command to the SET circuit breaker, and all the consumers of the MT line run out of supply. This is the only "blackout" that consumers will suffer. When their supply is restored, they will be assured that they will no longer run out of service more times, with the inconveniences already explained.
[0107]
[0108] d) When using such small intensities, the risk for the field operators performing the maneuvers disappears.
[0109]
[0110] e) This procedure is applicable when the line is in the Verification and Testing Regime, and as long as this situation does not change, the responsibility for the necessary maneuvers could fall on the work manager. The operator of the control center would be freed, while all maneuvers would be done more quickly.
[0111] f) When using such small intensities, all the risks listed in section f) of page 7 (risks and inconveniences) disappear. There will be no possibility of electrocutions or fires in the tests carried out.
[0112]
[0113] It is not the object of this patent application to claim any device included in it, since all of them exist in the market, and this has been commented on in several sections. There are dielectric strength meters, isolation poles, remote control technologies and remote control devices.
[0114]
[0115] What is claimed in this application is a new procedure, as it is not used in any electricity distribution company in the world, and of a clear industrial application in all of them, using existing devices and technologies, but combined in a useful and new way for the application of the procedure.
[0116] In the operating rules of electric power distribution companies there are two fundamental concepts to understand this new procedure:
[0117]
[0118] - Voltage Source: Any point of an electrical installation where there is voltage.
[0119] - Possible Voltage Source: Any point of an electrical installation where there may be voltage, and that when the installation is in discharge it is not foreseeable that it exists, but it could exist unexpectedly for the following reasons:
[0120]
[0121] 1) Lightning strike in case of storm, at some point in the installation.
[0122]
[0123] 2) Drop a cable from another power line that crosses it at some point.
[0124]
[0125] 3) Inductions from another line that shares supports.
[0126]
[0127] 4) Connection of a generator set of a tooth that is supplied from the line, without having disconnected its installation from the rest of the line.
[0128]
[0129] 5) Other causes.
[0130]
[0131] For example, if we open the disconnector F of FIG. 1, we will have a Voltage Source: The disconnector terminals that are in tension. The other terminals are without voltage and are considered to be electrically isolated from the Voltage Source. However, there will be at least five Possible Voltage Sources, one for each transformation center, since there is a possibility that in each of them a customer connects a generator set in the wrong way, without first disconnecting its installation from the power grid. Or if there is a storm at that time, any lightning point on the line can hit a lightning strike, so there are also possible sources of tension.
[0132]
[0133] Special mention is required of the electricity generating parks such as photovoltaic, wind, cogenerators, etc., which are configured so that if there is a breakdown in the power line to which they inject energy, they disconnect from it. But automation can fail.
[0134]
[0135] Current electrical stiffness meters, in the field of electric power distribution, are only used to measure the dielectric strength of a UNDERGROUND cable in Verification and Testing Regime, with the two cable ends isolated from the network with an effective cut . The cable to be tested has no intermediate branch to any other installation.
[0136] Under these conditions we have the insulated voltage source cable and there can also be no possible voltage source. In this way the operator who manages the device has no chance of receiving any electric shock. Work with total security.
[0137] The new procedure proposed in this patent application uses an adapted dielectric strength meter, valid for any MT, AIR or UNDERGROUND line, with the only condition that all Voltage Sources are open. It is not necessary to open the Possible Voltage Sources because the operator who manages the device will not contact the MT line, and therefore will work safely.
[0138]
[0139] Brief description of the drawings
[0140]
[0141] Both in the background of the invention and in the explanation thereof, I have relied on several drawings to complement the description that has been made, in order to help a better understanding of the invention. The drawings are summarized as follows:
[0142] Figure 1: Example of an orthogonal scheme that represents the distribution of a MT line with its corresponding transformation and sectioning centers, in which a fault has been simulated in a section thereof, in the derivation to CTF4.
[0143] Figure 2: Shows the placement on a support of an adapted mobile dielectric strength meter (1) (RDM), connected to a phase of the line with a cable (2) and a terminal (4), and grounded with another cable ( 2) and a spike of earth (3).
[0144] Figure 3: Example of an orthogonal scheme representing three MT 5 line cells (1,2 and 3). In one of them (3) an adapted fixed dielectric strength meter (4) (RDF) has been placed. Figure 4: Actual physical appearance of cell 3. The RDF (4) appears with its three phase connections and one neutral.
[0145] Figure 5: It is the same orthogonal scheme of Figure 1, in which an example of strategic placement of RDM and RDF has been included.
权利要求:
Claims (2)
[1]
1. Procedure to isolate the damaged section in the 3rd Category power line, which consists in the injection in the broken line of a low intensity electrical signal, of the order of 20 mA or 30 mA and of a maximum continuous voltage equal to the simple line voltage (phase-to-earth voltage) in case of a ground fault; and of a low frequency alternating voltage, of the order of 0.05 hertz, and at most equal to the compound voltage (phase-phase voltage), in the case of isolated earth fault, that is, between phases; through the use of a mobile dielectric strength meter, governed by remote control, which is connected and disconnected to the damaged power line by means of insulating poles, characterized by the following stages:
a) Choose a point on the faulty power line where the mobile dielectric strength meter is to be placed, preferably in an area with a greater probability of failure according to the historical ones.
b) Open all Voltage Sources at the chosen point. It is not necessary to open the Possible Voltage Sources, nor the wind farms, photovoltaic, cogenerators, etc.
c) Check the absence of tension at the chosen point, of the three phases, with the pole of absence of tension check.
d) If there is no voltage at any stage, which is the normal situation, the device is placed by holding it on a pole, or in a transformation center. One of the device's cables is connected to a ground pin, and the other cable is connected to one of the phases by using an insulating pole, always away from the device and the cables, with the use of a clamp terminal .
e) If voltage appears at any stage, the procedure is suspended until it is determined where the tension comes from.
f) Once the device has been connected to one of the phases, the dielectric strength of the unit is measured, the device being governed by remote control and maximum line tension applied. If the phase withstands the applied voltage it means that the earth fault is not in this phase. With the use of the insulating pole, the cable with its terminal is changed to another phase and the process is repeated. So until detecting which of the three phases is damaged.
g) Once the faulty phase has been detected, we keep the device connected to it. Using the trial-error method, we section the different sections of the line. In each section that we section we do a dielectric strength test. If the device gives us the phase failure device, it means that the fault is "upstream" of the open disconnector. If the line withstands the voltage, it means that the fault is "downstream" of the open disconnector. In this way we are testing the different sections until we identify which of them is the fault. You can no longer do tests because the section identified has no more disconnectors to maneuver.
h) The damaged section is left isolated (or open), and the dielectric strength meter is removed with the insulating pole. At this time, the entire line can be energized, and the power supply restored to all customers, except for the broken and isolated section.
i) In the event that the fault was a short circuit between phases, the device cables would be connected in the faulty phases and an alternating voltage would be injected. The procedure would be the same as described.
[2]
2. Procedure to isolate the damaged section in the 3rd Category power line, which consists in the injection in the broken line of a low intensity electrical signal, of the order of 20 mA or 30 mA and of a maximum continuous voltage equal to the simple line voltage (phase-to-earth voltage) in case of a ground fault; and of a low frequency alternating voltage, of the order of 0.05 hertz, and at most equal to the compound line voltage (phase-phase voltage), in the case of isolated earth fault, that is, between phases; by using a fixed dielectric strength meter, telecontrolled with GPRS technology, and placed inside a line sectioning cell, which in turn is assembled with other line cells, inside a transformation center or distribution center also telecontrolled and strategically located. It is characterized by the following stages:
a) When you open the Medium Voltage circuit breaker in the High Voltage-Medium Voltage electrical substation, due to a breakdown in the Medium Voltage line, the Energy Control Center establishes a connection with the dielectric strength meter, and with transformation center or distribution center where the meter is placed.
b) Check that there is no tension in bars. If there is no voltage, which is the normal situation, the switch-disconnector of the cell where the meter is located is closed. The dielectric strength meter is turned on and a test is made to check which phase or phases are in insulation failure. If it is confirmed that there is an insulation fault, there really is a fault in the line.
c) If voltage appears on bars, the procedure is suspended until the source of the tension is determined.
d) It begins with trial-error tests. The different sections of the broken line are sectioned, and with each section a dielectric strength test is made, and in this way the healthy sections are discarded, that is, in which the fault is not found.
e) Once the damaged section is identified, it is left isolated for later repair.
f) The supply to the rest of the line will be restored.
类似技术:
公开号 | 公开日 | 专利标题
US9385522B2|2016-07-05|Low fault current isolator system
ES2538455T3|2015-06-22|Active electronic grounding system for use in high voltage distribution networks
Theron et al.2018|Tutorial on high impedance fault detection
ES2719933B2|2020-07-01|Procedure to isolate the faulty section using an adapted dielectric strength meter, in 3rd category distribution networks
Panth2014|Reasons for failure of transmission lines and their prevention strategies
CN207780156U|2018-08-28|A kind of low-voltage circuit trouble shoot device
ES2666495T3|2018-05-04|Failure protection system for a network area of a high voltage distribution network
Dimov et al.2020|Influence of the type of electrical distribution network on the indices of continuity of the power supply
Hunt et al.1940|Sensitive ground protection for radial distribution feeders
Watson2010|Impact of the Darfield earthquake on the electrical power system infrastructure
Li et al.2017|Live-line operation and maintenance of power distribution networks
Bagchi et al.2018|A Holistic Approach to Develop a Robust Distribution Network with Integrated Protection and Automation Management System for a Next Generation Electric Utility
Jardini et al.2009|On the analysis and evaluation of a transmission line upgrading assisted by line arresters
Kachanov et al.2021|Improving the functioning efficiency of 6-10 kV electrical networks with isolated neutral in conditions of single-phase ground faults
Telegin et al.2019|Increasing the Efficiency of Operation of Fault Indicators at Long-Distance Branched Overhead Lines
Scholtz2011|Improved transient earth fault clearing on solid and resistance earthed MV netwworks
Pocthier et al.2019|Improve your SAIDI with Advanced Fault Passage Indication
Škumát et al.2019|Open Phase Fault Localization in a Medium Voltage Distribution Grid Using Smart Meters
Achleitner et al.2007|Overall protection in decentralized wind power plants and decentralized grids
ES2448820A2|2014-03-17|Method and system to limit the triggers of a differential. |
OLUSOLA2016|DESIGN OF 500kVA, 11/0.415 kV SUBSTATION
ES1274659U|2021-07-22|EQUIPMENT FOR DETECTION OF FAULTS OR EARTH DEFECTS IN ELECTRIC POWER GENERATION FACILITIES WITH PHOTOVOLTAIC MODULES |
Haluza1996|Lightning, ground potential rise, and electrical damage; protecting wayside equipment on the MTA Long Island Rail Road
Santos et al.2014|Effective and simple measures to improve the electric power distribution systems service continuity
Lebedev et al.2021|Development of a Method for Location of a Damaged Overhead Power Line Section in Case of Single-Phase Earth Faults
同族专利:
公开号 | 公开日
WO2020104711A1|2020-05-28|
ES2719933B2|2020-07-01|
引用文献:
公开号 | 申请日 | 公开日 | 申请人 | 专利标题
CN102841299A|2011-06-21|2012-12-26|易丰兴业有限公司|Direct-current power supply insulation fault detection circuit|
EP2574939A2|2011-09-29|2013-04-03|Bender GmbH & Co. KG|Isolation fault detection device and device for insulation fault localisation in an unearthed power supply network|
EP2860838A1|2013-10-08|2015-04-15|Rockwell Automation Technologies, Inc.|Apparatus and method for automatic ground fault location determination in high resistance grounded motor drive system|
EP3136526A1|2015-08-25|2017-03-01|GE Energy Power Conversion Technology Ltd|Ground fault protection methods|
CN207586348U|2017-10-23|2018-07-06|国网山东省电力公司荣成市供电公司|A kind of distribution network failure detection device|
CN108398619A|2018-02-24|2018-08-14|吴星笑|A kind of power grid fault detection system|
法律状态:
2019-07-16| BA2A| Patent application published|Ref document number: 2719933 Country of ref document: ES Kind code of ref document: A1 Effective date: 20190716 |
2020-07-01| FG2A| Definitive protection|Ref document number: 2719933 Country of ref document: ES Kind code of ref document: B2 Effective date: 20200701 |
优先权:
申请号 | 申请日 | 专利标题
ES201800265A|ES2719933B2|2018-11-23|2018-11-23|Procedure to isolate the faulty section using an adapted dielectric strength meter, in 3rd category distribution networks|ES201800265A| ES2719933B2|2018-11-23|2018-11-23|Procedure to isolate the faulty section using an adapted dielectric strength meter, in 3rd category distribution networks|
PCT/ES2019/000051| WO2020104711A1|2018-11-23|2019-07-05|Method for isolating a faulty section using an adapted dielectric strength meter in category 3 distribution networks|
[返回顶部]