专利摘要:
Ship for the transport and installation of offshore wind units. The present invention refers to a ship for the transport and installation of offshore wind units that presents in plan a shape that mediates between a "U" inside and a "V" on its outside, similar to the outline of a horseshoe that it is self-propelled, which has a competent dynamic positioning system and has a system of lowering and hoisting of cable jacks assisted by ballast subsystems, fenders, moorings and mechanical/hydraulic/electrical devices to carry out safely and autonomously the operations of transportation and installation of offshore wind units and/or their foundations. (Machine-translation by Google Translate, not legally binding)
公开号:ES2607428A1
申请号:ES201531364
申请日:2015-09-24
公开日:2017-03-31
发明作者:Antonio NAVARRO ARANDA;Cristina HEREDERO BUENO;César YANES BAONZA
申请人:Universidade da Coruna;Iberdrola Renovables Energia SA;
IPC主号:
专利说明:

image 1
image2
image3
image4
image5
image6


control the stability and mass distribution of the wind unit and the vessel by filling and emptying by means of the ballast system of compartments or tanks arranged both in a foundation (3) of the wind unit and in the ship itself.
5 The vessel for the transport and installation of offshore wind units also comprises a dynamic positioning system designed to provide substantially the same positioning capacity regardless of the direction of wind, current and swell, comprising a set of thrusters (4), preferably two propellers (4) arranged at the stern ends of the half-shells and two propellers (4)
10 arranged adjacent to the vertex on the bow of the ship.
The ship for the transport and installation of offshore wind units also includes a cargo trenching system for transport, consisting of the cable jacks (1) of the lowering and hoisting system together with a complementary system of defenses
15 (5) disposed on the inner sides of the ship and at the bottom, which comes into contact with the wind unit to be installed and works either by friction or by compression efforts in the contact areas between the wind unit and the ship. This complementary system of defenses (5) allows that during the transport phase the relative movements between the ship and the cargo are restricted.
20 Preferably, the lashing system further comprises a sling system tensioned by winches and / or hydraulic cylinders (6) that hold the wind unit to the vessel.
The vessel object of the present invention eliminates the need to use auxiliary means during transport and installation of the wind unit, since it comprises a dynamic positioning system, landing / lifting and ballast equipment, and a system of control of the operation that allows the installation of the wind unit autonomously.
30
8
权利要求:
Claims (1)
[1]
image 1
image2
类似技术:
公开号 | 公开日 | 专利标题
ES2764375T3|2020-06-03|Improvements related to component handling, in particular handling of wind turbine components
SG188145A1|2013-03-28|Offshore drilling vessel
CN107207078B|2019-07-26|Ship is set to enter the diving ship of dry dock
ES2607428A1|2017-03-31|Ship for the transport and installation of offshore wind units |
CN203937832U|2014-11-12|A kind of combination is refuted
PH12017502095A1|2018-05-07|Hybrid ship using wind-powered propulsive force as auxiliary
RU2390460C1|2010-05-27|Complex to surface and carry sunken submarines and other ships
GB201120015D0|2012-01-04|Vessel for offshore transport and handling means, method and uses hereof
US20150197317A1|2015-07-16|Assembly for transporting a boat lift
RU2015139928A|2017-04-06|SHIP COMBINING FUNCTIONS FOR CARRYING HEAVY LOADS AND LOGISTICS
PT2377801E|2013-08-29|Method of serving a complex including two and more mobile wharf boom cranes
RU2377155C1|2009-12-27|Marine cargo ship for lifting, loading-unloading and transportation of sunk objects into receiving centre
RU2710876C1|2020-01-14|Ship-lifting modular docking system
US11208179B2|2021-12-28|Maintenance facility, power generation facility, and maintenance method for device
JP5684220B2|2015-03-11|How to install a buoy
NL1026591C2|2006-01-09|Manipulation method for carrying out work on object on water, e.g. ship, by floating object above platform sunk using platform and then raising platform on its legs
ES2631010T3|2017-08-25|Vessel with vertical draft system
UA68677U|2012-04-10|Floating unloader
KR100926890B1|2009-11-16|A floating pier including a means of moving a bridge
CN104149945A|2014-11-19|Combined barge
KR20170030200A|2017-03-17|Offshore structure installation vessel
ES2468765B1|2015-03-31|Marine platform for dredging sludge treatment
ES1212463Y|2018-09-07|Ship with device for hoisting and lowering sails and wind generator built into the mast
ES2370056T3|2011-12-12|VESSEL OF FACILITIES IN DEEP WATERS.
RU2600963C1|2016-10-27|Increased capacity crane
同族专利:
公开号 | 公开日
ES2607428B1|2018-01-09|
引用文献:
公开号 | 申请日 | 公开日 | 申请人 | 专利标题
WO2011028102A2|2009-09-04|2011-03-10|Itrec B.V.|Offshore wind turbine installation|
WO2011093704A1|2010-01-28|2011-08-04|P&R Systems|Maintenance of an offshore wind farm making use of an assembly of a floating harbour ship and a plurality of shuttle vessels|
EP2581336A1|2010-06-09|2013-04-17|Sinovel Wind Group Co., Ltd|Multifunctional platform of wind power generating unit and blade disassembling method|
US20120183359A1|2011-01-14|2012-07-19|The Glosten Associates, Inc.|Installation method for water-submersible platforms and installation vessel|CN111425356A|2020-03-31|2020-07-17|青岛嘉恒新能源设备有限公司|Splicing device for tower cylinders of wind driven generators|
法律状态:
2018-01-09| FG2A| Definitive protection|Ref document number: 2607428 Country of ref document: ES Kind code of ref document: B1 Effective date: 20180109 |
优先权:
申请号 | 申请日 | 专利标题
ES201531364A|ES2607428B1|2015-09-24|2015-09-24|Ship for the transport and installation of offshore wind units|ES201531364A| ES2607428B1|2015-09-24|2015-09-24|Ship for the transport and installation of offshore wind units|