专利摘要:
An open caisson construction structure comprising: cast-in-place piles (1) symmetrically placed at the bottom of a foundation pit; Tubular steel pillars (2) connected to each cast-in pile (1), the lower end of each tubular steel pillar (2) being connected to the upper end of the corresponding cast-in pile (1); a steel-constructed platform (4) connected to all of the tubular steel columns (2), the steel-constructed platform (4) being oriented perpendicular to the tubular steel columns (2); Lifting devices (5) provided at the top of each tubular steel column (2); Connecting posts (6) each connected to the upper end of each lifting device (5); an open caisson (7) which surrounds a space bounded by the tubular steel columns (2), with steel brackets (8) being arranged on the inner wall of the open caisson (7) so that the steel brackets correspond to the respective tubular connecting columns positionally, and those with the same tubular connecting columns to be connected are axially spaced from one another along the open caisson, and the steel consoles (8) are supported on the tubular connecting columns (6). A method of manufacturing an open caisson construction is also contemplated. The in-situ concrete piles (1), tubular steel columns (2) and steel brackets (8) serve as guides for the lowering of the open caisson (7), while the lifting devices (5) are provided to adjust the height of the tubular connecting supports (6), see above that the open caisson (7) remains vertical during its lowering.
公开号:CH715226B1
申请号:CH01548/19
申请日:2018-06-22
公开日:2021-05-14
发明作者:Long Libo;Yu Jiajun;Qi Jianwen
申请人:Shanghai Construction No 2 Group Co Ltd;
IPC主号:
专利说明:

TECHNICAL PART
This invention relates to an open caisson structure and construction.
BACKGROUND
The open caisson construction is a technology for creating a deep foundation or an underground structure. The open caisson construction is done by making a reinforced concrete caisson on the ground or in an excavation and excavating the earth inside the caisson layer by layer after the concrete strength has reached a certain level. With the soil surface getting deeper and deeper in the course of the excavation, the caisson overcomes the frictional resistance on the side surfaces and the reaction on the cutting edges by its own weight or by other measures, so that it gradually subsides until it reaches the design height, and then the Soil sealing construction carried out.
The open caisson structure has the following advantages: Allows building at great depth (up to over 50 meters) in a narrow building area with minimal impact on the environment; Applicability in regions with complex geological and hydrological conditions; Avoid the use of complicated machines; and reducing the amount of soil that needs to be dug, transported and backfilled compared to large-scale excavation. Nevertheless, it also has some disadvantages such as relatively more process steps, high technical requirements and difficult quality control. Of these, the slope correction during settlement is most critical, since any slope that is not corrected immediately can become uncorrectable after the open caisson is set.
SUMMARY OF THE INVENTION
It is an object of the present invention to provide an open caisson construction structure and method that solve problems such as poor squareness checking accuracy, tilt, sudden drop that can occur in soft ground, and complex work in building the operating platform.
To this end, the present invention provides an open caisson structural structure comprising:
A plurality of in-situ concrete piles which can be arranged symmetrically on a floor of a construction pit to be excavated;
Tubular steel columns which are arranged on the respective in-situ concrete piles, each of the tubular steel columns having a lower end which is connected to an upper end of one of the corresponding in-situ concrete piles and can extend to the ground from the excavation to be built;
A platform built of steel that vertically connects all tubular steel columns;
Lifting devices arranged on the respective tubular steel columns;
Tubular connecting columns mounted on the respective lifting devices; and
An open caisson surrounding a space bounded by the tubular steel columns, with an inner wall on which steel brackets are arranged so that the steel brackets are aligned with the respective tubular connecting columns, and the steel brackets to be connected to the respective tubular connecting columns axially are spaced from one another along the open caisson, the inner wall adjoining the tubular steel columns and the tubular connecting columns supporting the steel brackets.
In addition, the steel constructed platform in the structure may comprise: a ring beam connecting all tubular steel columns; and horizontal beams connected within the ring beam.
In addition, steel struts can be connected to the floor of the steel constructed platform and tubular steel columns in the construction.
In addition, the steel-fabricated platform can have recesses in the construction, a crane being arranged on the steel-fabricated platform and a clamshell excavator being arranged in the excavation under the steel-fabricated platform.
In addition, the lifting devices can be bidirectional lifting devices.
In addition, in the structure, each of the steel brackets may be an L-shaped structure composed of a first plate and a second plate connected to the first plate, the first plate being attached to the inner wall of the open caisson, and the second plate is supported on one of the corresponding tubular connecting columns.
In addition, the structure may further comprise horizontal reinforcing members each vertically attached to the first plate of one of the corresponding steel brackets at one end and supported against a side surface of one of the corresponding tubular connecting columns at the other end.
In addition, the structure can further comprise:
Displacement and force sensors attached to each of the lifting devices; and
A controller which is connected to the lifting devices and the displacement and force sensors.
In another aspect, the present invention provides a method of making an open caisson structure comprising:
Arranging a plurality of in-situ concrete piles symmetrically on a floor of a construction pit to be excavated and arranging tubular steel columns on respective in-situ concrete piles, each of the tubular steel columns having a lower end which is connected to an upper end of one of the corresponding in-situ concrete piles and extends to the ground from the excavated excavation extends;
Excavation of the construction pit at a certain height and construction of a steel-fabricated platform that connects all tubular steel columns vertically;
Attaching lifting devices to the respective tubular steel columns;
Connecting tubular connecting columns to the top of the respective lifting devices;
Arranging steel brackets on an inner wall of an open caisson so that the steel brackets correspond positionally with the respective tubular connecting columns and the steel brackets to be connected to the same tubular connecting column are axially spaced along the open caisson; and
Arranging the open caisson to create a space delimited by the tubular steel columns, the inner wall of the open caisson adjoining the tubular steel columns and the steel brackets being supported on respective tubular connecting columns.
Furthermore, the method comprises the symmetrical arrangement of the in-situ concrete piles on the bottom of the excavation pit to be excavated and the arrangement of the tubular steel columns at the upper end of the respective in-situ concrete piles:
Excavation of pile holes in the bottom of the construction pit and insertion of reinforcement cages for the in-situ concrete piles in the pile holes;
Introducing concrete into the reinforcement cages up to a first design height; and
Introduction of the tubular steel columns by a hydraulic verticality compensation system in the concrete, which is poured in corresponding reinforcement cages at a second design height.
Furthermore, the method comprises the construction of the steel-constructed platform that connects all tubular steel columns:
Connecting all tubular steel columns with a ring carrier; and
Connecting horizontal tubular steel girders within the ring girder.
In addition, after assembling the steel-constructed platform that connects all of the tubular steel columns, the method further comprises:
Connecting steel struts to a floor of the steel constructed platform and the tubular steel columns.
Furthermore, the method of building the steel-constructed platform connecting all of the tubular steel columns includes:
Construction of a steel-fabricated platform with recesses, the steel-fabricated platform connecting all tubular steel columns;
Placing a crane on the steel-built platform; and
Lifting a clamshell excavator with the crane in order to move it through one of the recesses into the excavation under the steel-fabricated platform.
Furthermore, in the method, the lifting devices can be bidirectional lifting devices.
Furthermore, in the method, the steel brackets are arranged on the inner wall of the open caisson in such a way that the steel brackets correspond in position to the respective tubular connecting columns and the steel brackets to be connected to the same tubular connecting column are axially spaced from one another along the open caisson:
Providing the steel brackets each of which is an L-shaped structure composed of a first plate and a second plate connected to the first plate;
Attaching the first panels to the inner wall of the open caisson; and
Supporting the steel consoles on the tubular connecting columns, wherein the supporting comprises supporting the second plates on the tubular connecting columns.
In addition, the method may further comprise: prior to supporting the second plates on the tubular connecting columns,
Vertically attaching horizontal reinforcement members at one end to the first panels; and
After supporting the second plates on the tubular connecting columns,
Pressing the horizontal reinforcing elements at the other end against side surfaces of the tubular connecting columns.
In addition, after the steel brackets have been supported on the tubular connecting columns, the method may further comprise:
Providing displacement and force sensors on each of the lifting devices; and
Connecting the lifting devices and the displacement and force sensors to a controller;
Wherein the controller detects displacements of the tubular connecting columns from the displacement sensors, and if there is a difference between the displacements, the controller controls the lifting devices to adjust the tubular connecting columns in height, according to the data from the force sensors about forces on the bidirectional Lifting devices.
In order to solve the problems of lowering the open caisson, such as poor accuracy in checking the perpendicularity, inclination, sudden lowering that can occur on soft ground, and complex work in the construction of the operating platform, the present invention provides a (tubular steel ) Pillar and (in-situ emphasis) pile-guided controlled structure, in which the pile cast on site and the tubular steel column inserted into it form a column and pile structure that is arranged on the inside of the open caisson as a vertical support. In addition, the pillar and pile structures are connected to each other by a steel platform so that the open caisson can steadily sink. Furthermore, a tubular connecting column connected to the top of each bidirectional lifting device and a steel bracket supported on the tubular connecting column serve as important structures for guiding in the setting of the open caisson. In this way, the earth can be removed from the foundation pit surrounded by the tubular steel columns, followed by the dismantling of the lowest steel consoles A, the open caisson can sink under its own weight until the steel consoles B previously arranged above the removed steel consoles A attach to the tubular connecting column reached a point where the steel brackets B can be supported by the tubular connecting column. In this way, the new lowermost steel consoles, which are carried by the tubular connecting columns, can be successively removed so that the open caisson can sink continuously and successively under the influence of its own weight. In addition, at any inclination of the open caisson that occurs during lowering, the lifting devices can be actuated to adjust the height of the tubular connecting columns to ensure that the open caisson remains vertical during lowering, thereby maintaining the squareness and stability of the open one Caisson is effectively controlled in the lowering, which allows a simple and inexpensive construction.
BRIEF DESCRIPTION OF THE DRAWINGS
Fig. 1 is a schematic illustration of an open caisson construction in accordance with one embodiment of the present invention.
Figure 2 is a top plan view of an open caisson structure in accordance with an embodiment of the present invention.
Figure 3 is an enlarged view of a tubular steel column showing the connections between the tubular steel column and other structures in accordance with an embodiment of the present invention.
Fig. 4 schematically illustrates the connection between an in-situ concrete pile and a tubular steel column according to an embodiment of the present invention.
Figure 5 schematically illustrates an open caisson construction performed under a first condition in accordance with an embodiment of the present invention.
Figure 6 schematically illustrates an open caisson construction performed under a second condition in accordance with an embodiment of the present invention.
Figure 7 schematically illustrates an open caisson construction performed under a third condition in accordance with an embodiment of the present invention.
DETAILED DESCRIPTION
The aforementioned objects, features and advantages of the present invention will be more clearly and better understood from the following detailed description of some specific embodiments, which is to be read in conjunction with the accompanying drawings.
As shown in Figures 1 through 4, the present invention is an open caisson construction comprising:
A plurality of in-situ concrete piles 1, which can be arranged symmetrically on the bottom of a construction pit to be excavated;
Steel pipe columns 2 arranged on top of the respective in-situ concrete piles 1, each of the steel pipe columns 2 having a lower end connected to an upper end of a corresponding one of the in-situ concrete piles 1 and extending to the bottom 3 of the excavation pit to be removed can;
A platform 4 made of steel, which is vertically connected to all of the tubular steel columns 2;
Lifting devices 5 arranged on top of the respective tubular steel columns 2, each of the lifting devices 5 being able to be connected to the upper end of a corresponding one of the tubular steel columns 2 by means of anchor bolts and washers;
Tubular connecting columns 6 connected to the top of the respective lifting device 5, wherein, as shown in Fig. 3, each of the tubular connecting columns 6 can be connected via a flange 13 to a corresponding one of the lifting devices 5; and
An open caisson 7, which surrounds a space delimited by the tubular steel columns 2, the open caisson 7 having an inner wall on which steel brackets 8 are arranged in positional correspondence with the respective tubular connecting columns 6, which are connected to the same tubular connecting columns 6 connecting steel brackets 8 are axially spaced apart from one another along the open caisson, the inner wall adjoins the tubular steel columns 2 and the steel brackets 8 are supported on the respective tubular connecting columns 6.
In particular, as shown in Fig. 3, a plurality of threaded holes can be provided in the inner wall of the open caisson at each of several structural elevations, so that the steel brackets 8 can be easily attached by the connection between the screws 12 and the threaded holes .
In order to solve the problems in lowering the open caisson, such as poor accuracy in the perpendicularity control, inclination, sudden lowering that can occur on soft ground, and complex work in the construction of the operating platform, the present invention provides a (steel pipe -) Pillar and (in-situ emphasis) pile guide construction, in which the pile cast on site and the tubular steel column inserted into it form a column and pile structure that is arranged on the inside of the open caisson as a vertical support. In addition, the pillar and pile structures are connected to each other by a steel platform so that the open caisson can steadily sink. Furthermore, a tubular connecting column connected to the top of each bidirectional lifting device and a steel bracket supported on the tubular connecting column serve as important structures for guiding in the setting of the open caisson. In this way, the earth can be removed from the foundation pit surrounded by the tubular steel columns, followed by the dismantling of the lowest steel consoles A, the open caisson can sink under its own weight until the steel consoles B previously arranged above the removed steel consoles A attach to the tubular connecting column reached a point where the steel brackets B can be supported by the tubular connecting column. In this way, the new lowermost steel consoles, which are carried by the tubular connecting columns, can be successively removed so that the open caisson can sink continuously and successively under the influence of its own weight. In addition, at any inclination of the open caisson that occurs during lowering, the lifting devices can be actuated to adjust the height of the tubular connecting columns to ensure that the open caisson remains vertical during lowering, thereby maintaining the squareness and stability of the open one Caisson is effectively controlled in the lowering, which allows a simple and inexpensive construction.
As shown in Fig. 2, the steel constructed platform according to an embodiment of the present invention may include: a ring beam connecting all of the tubular steel columns; and horizontal steel girders connected within the ring girder.
In this case, the steel-constructed platform is constructed by the ring girder and the horizontal steel girders, and the horizontal steel girders can be completely welded to the ring girder to ensure that the steel-constructed platform has sufficient strength.
As shown in Fig. 1, according to one embodiment of the present invention, steel struts 11 can be connected to the floor of the steel-constructed platform and the tubular steel columns in order to achieve additional strengths.
As shown in Fig. 1, the steel-constructed platform according to an embodiment of the present invention can have recesses, a crane 9 being arranged on the steel-constructed platform 4 and a clamshell excavator arranged in the excavation under the steel-constructed platform.
In this case, the steel-constructed platform 4 can serve as a foundation for large equipment to be applied to the structure for building the crane 9 and the clamshell excavator and for lifting the required construction materials. This can improve the efficiency and quality of the construction, lead to cost savings, reduce the construction risk and guarantee quality assurance. For example, the crane can be placed on the steel-constructed platform and configured to lift the clamshell excavator to move it down into the foundation pit under the steel-constructed platform through one of the recesses so that the clamshell excavator can dig the earth out of the foundation pit and then can lift the excavated earth from the foundation pit for removal.
According to an embodiment of the present invention, the lifting devices can be bidirectional lifting devices which are able to flexibly adjust the height of the tubular connecting columns.
As shown in Figs. 1 and 3, according to an embodiment of the present invention, each of the steel brackets 8 may be an L-shaped structure composed of a first plate and connecting a second plate to the first plate. The first plate is fastened to the inner wall of the open caisson 7, the second plate is supported on the tubular connecting columns 6.
As shown in Figures 1 and 3, the open caisson construction according to an embodiment of the present invention may further comprise: horizontal reinforcement members 10 each attached perpendicularly to the first plate of a corresponding one of the steel brackets at one end and against a side surface of a corresponding one of the tubular connecting columns are supported at the other end, each of the horizontal reinforcing elements 10 also being perpendicular to a corresponding one of the tubular connecting columns 6.
According to one embodiment of the present invention, the open vessel construction may further comprise:
Displacement and force sensors provided on each of the lifting devices 5; and
A control that is connected to the displacement and force sensors and the lifting devices.
In this case, the displacement and force sensors can be provided on the bidirectional hoists 5 to collect displacement and force results via the tubular connecting columns 6, and the controller can be configured to contract / expand the hoists for accurate intelligent control of the open caisson in its settlement. In particular, the control can detect displacements of the tubular connecting columns from the displacement sensors. If there is a difference between the displacements, the controller can control the lifting devices to adjust the height of the tubular connecting columns according to the data from the force sensors about forces on the bidirectional n lifting devices. This enables precise intelligent control to be achieved.
The present invention also provides a method of making an open caisson structure comprising the following steps.
As shown in FIG. 5, in step S1 in step S1 a plurality of in-situ concrete piles 1 are arranged symmetrically on the bottom of a construction pit to be excavated and tubular steel columns 2 are arranged over the respective in-situ concrete piles 1. Each of the tubular steel columns has a lower end which is connected to an upper end of a corresponding one of the in-situ concrete piles 1 and extends to the bottom 3 of the excavation to be constructed.
As shown in FIG. 6, in step S2 the construction pit is excavated to a certain depth and a steel-fabricated platform 4 is built which connects all steel pipe columns.
As shown in Fig. 7, the lifting devices 5 are arranged on the respective tubular steel columns in step S3.
Each of the lifting devices can be connected to the top of a corresponding one of the tubular steel columns by means of anchor bolts and washers.
As shown in FIG. 7, the tubular connecting column 6 is connected to the upper side of the respective lifting device 5 in step S4.
Each of the tubular connecting columns 6 can be connected to a corresponding one of the lifting devices 5 via a flange 13.
As shown in Fig. 7, in step S5 steel brackets 8 are arranged on an inner wall of an open caisson 7 so that the steel brackets 8 correspond to the respective tubular connecting columns 6 positionally and the steel brackets 8 to be connected to the same tubular connecting column 6 axially along of the open caisson are spaced apart.
As shown in FIG. 7, in step S6 the open caisson 7 is arranged so that it encloses a space delimited by the tubular steel columns 2 so that the inner wall of the open caisson 7 adjoins the tubular steel columns 2 and the steel brackets 8 the respective tubular connecting columns 6 are supported.
In order to solve the problems in the lowering of the open caisson, such as poor accuracy in the perpendicularity control, inclination, sudden lowering that can occur on soft ground, and complex work in the construction of the operating platform, the present invention provides a (steel pipe -) Pillar and (in-situ emphasis) pile guide construction, in which the pile cast on site and the tubular steel column inserted into it form a column and pile structure that is arranged on the inside of the open caisson as a vertical support. In addition, the pillar and pile structures are connected to each other by a steel platform so that the open caisson can steadily sink. Furthermore, a tubular connecting column connected to the top of each bidirectional lifting device and a steel bracket supported on the tubular connecting column serve as important structures for guiding in the setting of the open caisson. In this way, the earth can be removed from the foundation pit surrounded by the tubular steel columns, followed by the dismantling of the lowest steel consoles A, the open caisson can sink under its own weight until the steel consoles B previously arranged above the removed steel consoles A attach to the tubular connecting column reached a point where the steel brackets B can be supported by the tubular connecting column. In this way, the new lowermost steel brackets, which are carried by the tubular connecting columns, can be successively removed so that the open caisson can sink continuously and successively under the influence of its own weight. In addition, the lifting devices can be operated at any inclination of the open caisson during the lowering to adjust the height of the tubular connecting columns to ensure that the open caisson remains vertical during the lowering, thereby ensuring the squareness and stability of the open caisson in the Lowering is effectively controlled, which enables a simple and inexpensive construction.
According to one embodiment of the present invention, step S1, the symmetrical arrangement of the plurality of in-situ concrete piles on the bottom of the excavation to be excavated and the arrangement of the tubular steel columns on the respective in-situ concrete piles, include:
Digging pile holes in the bottom of the construction pit and inserting reinforcement cages for the in-situ concrete piles into the pile holes, as shown in FIG. 5;
Introducing concrete into the reinforcement cages up to a first design height; and
Insertion of each of the tubular steel columns into the concrete, which is poured in a corresponding one of the reinforcement cages, by a high-precision hydraulic verticality adjustment system HDC to a second design height.
According to an embodiment of the present invention, the step S2, which involves the construction of the steel-constructed platform connecting all the steel pipe columns, may include:
Connecting all tubular steel columns with a ring carrier; and
Joining horizontal steel girders within the ring girder.
In this case, the horizontal steel beams can be completely welded to the ring beam to ensure that the steel-fabricated platform has sufficient strength.
According to an embodiment of the present invention, the method in step S2 after the construction of the steel-constructed platform that connects all of the tubular steel columns may further include:
Connecting the steel struts 11 to the floor of the steel-constructed platform and the tubular steel columns in order to achieve additional strengths, as shown in FIG.
According to an embodiment of the present invention, the step S2, which involves the construction of the steel-constructed platform that connects all of the tubular steel columns, may include:
Construction of a steel-fabricated platform with recesses that connects the entire tubular steel column;
Placing a crane on the steel constructed platform; and
Lifting a clamshell excavator with the crane in order to move it through one of the recesses into the excavation under the steel-fabricated platform.
In this case, the steel-constructed platform can serve as a foundation for large equipment in order to be applied to the construction for the construction of the crane 9 and the clamshell excavator and for lifting the necessary construction materials. This can improve the efficiency and quality of the construction, lead to cost savings, reduce the construction risk and guarantee quality assurance. For example, the crane can be placed on the steel-framed platform and configured to lift the clamshell excavator to move it down into the foundation pit under the steel-framed platform through one of the recesses so that the clamshell digger dig the earth out of the foundation pit and then can lift the excavated earth from the foundation pit for removal.
According to an embodiment of the present invention, the lifting devices can be bidirectional lifting devices.
As shown in Fig. 7, the step S5, which arranges steel brackets on an inner wall of an open caisson so that the steel brackets correspond to the respective tubular connecting columns positionally and the steel brackets to be connected to the same tubular connecting support axially along the open caisson from each other are spaced, include:
Providing the steel brackets 8 each of which is an L-shaped structure composed of a first plate and a second plate connected to the first plate;
Fixing the first plates to the inner wall of the open caisson 7; and
Step S6, which supports the steel brackets on the tubular connecting columns, may include supporting the second plates on the tubular connecting columns 6.
As shown in Fig. 7, the method according to an embodiment of the present invention may further include the following, before the second plates are supported on the tubular connecting columns:
Vertically securing horizontal reinforcement members 10 at one end to the first panels; and
[0116] after supporting the second plates on the tubular connecting columns 6,
Pressing the horizontal reinforcing elements 10 at the other end against side surfaces of the tubular connecting columns 6.
According to an embodiment of the present invention, the method may further comprise, after supporting the steel brackets on the tubular connecting columns,
Providing displacement and force sensors on each of the lifting devices;
Connecting the lifting devices and the displacement and force sensors to a controller; and
Wherein the control detects displacements of the tubular connecting columns by the displacement sensors. If there is a difference between the displacements, the controller can control the lifting devices to adjust the height of the tubular connecting columns according to the data from the force sensors about forces on the bi-directional lifting devices.
In this case, the displacement and force sensors can be provided on the bidirectional hoists 5 to collect displacement and force results via the tubular connecting columns 6, and the controller can be configured to contract / expand the hoists for accurate intelligent control of the open caisson in its settlement. In particular, the control can detect displacements of the tubular connecting columns from the displacement sensors. If there is a difference between the displacements, the controller can control the lifting devices to adjust the height of the tubular connecting columns according to the data from the force sensors about forces on the bi-directional lifting devices. This enables precise intelligent control to be achieved.
It should be noted that the embodiments disclosed herein will be described step-by-step, with the description of each embodiment focusing on its differences from other embodiments. Reference may be made between the embodiments for the same or similar parts thereof.
权利要求:
Claims (17)
[1]
1. Open caisson construction structure comprising:a plurality of in-situ concrete piles (1) which can be arranged symmetrically on a floor (3) of a construction pit to be excavated;Steel pipe columns (2) which are arranged on the respective in-situ concrete piles (1), each of the steel pipe columns (2) having a lower end which is connected to an upper end of one of the corresponding in-situ concrete piles (1) and extends to the ground (3) can extend out of the excavation to be constructed;a platform (4) made of steel, which connects all tubular steel columns (2); Lifting devices (5) arranged on the respective tubular steel columns (2); tubular connecting columns (6) mounted on the respective jacks (5); andan open caisson (7) which surrounds a space delimited by the tubular steel columns (2), with an inner wall on which steel brackets (8) are arranged in such a way that the steel brackets (8) are aligned with the respective tubular connecting columns (6), and wherein the steel brackets (8) to be connected to the respective tubular connecting columns (6) are axially spaced from one another along the open caisson, the inner wall adjoining the tubular steel columns (2) and the tubular connecting columns (6) supporting the steel brackets (8).
[2]
2. An open caisson structural structure according to claim 1, wherein the platform (4) made of steel comprises: a ring beam connecting all of the tubular steel columns (2); and horizontal steel girders connected to the ring girder within the ring girder.
[3]
3. An open caisson construction structure according to claim 1, wherein steel struts (11) are connected to a bottom of the platform (4) made of steel and the tubular steel columns (2).
[4]
4. An open caisson construction structure according to claim 1, wherein the platform (4) made of steel has recesses, the platform (4) made of steel is a platform for a crane (9); and wherein the recesses are designed so that a clamshell excavator can be lifted with the crane (9) through one of the recesses into the excavation under the platform (4) made of steel.
[5]
5. An open caisson structural structure according to claim 1, wherein the lifting devices (5) are bidirectional lifting devices.
[6]
6. An open caisson structural structure according to claim 1, wherein each of the steel brackets (8) is an L-shaped structure consisting of a first plate and a second plate connected to the first plate, the first plate on the inner wall of the open caisson and the second plate is supported on one of the corresponding tubular connecting columns (6).
[7]
The open caisson structural structure of claim 6, further comprising horizontal reinforcement members (10) each vertically attached to the first plate of one of the respective steel brackets (8) at one end and against a side surface of one of the respective tubular connecting columns (6) at the other End are supported.
[8]
8. The open caisson structural structure of claim 1 further comprising:Displacement and force sensors attached to each of the lifting devices (5); anda control that is connected to the lifting devices (5) and the displacement and force sensors.
[9]
9. A method of making an open caisson structure comprising:Arranging a plurality of in-situ concrete piles (1) symmetrically on the bottom of a construction pit to be excavated and arranging tubular steel columns (2) on respective in-situ concrete piles (1), each of the tubular steel columns (2) having a lower end which connects with an upper end of one of the corresponding in-situ concrete piles (1) is connected and extends to the ground of the excavation pit;Excavation of the construction pit to a certain depth and construction of a platform (4) made of steel, which connects all tubular steel columns (2);Attaching lifting devices (5) to the respective tubular steel columns (2);Connecting tubular connecting columns (6) to the top of the respective lifting devices (5);Arranging steel consoles (8) on an inner wall of an open caisson (7) so that the steel consoles (8) correspond in position to the respective tubular connecting columns (6) and axially along the steel consoles (8) to be connected to the same tubular connecting column (6) the open caisson (7) are spaced apart from one another; andArranging the open caisson (7) to create a space delimited by the tubular steel columns (2), the inner wall of the open caisson (7) adjoining the tubular steel columns (2) and the steel brackets (8) on respective tubular connecting columns (6) are supported.
[10]
10. The method according to claim 9, wherein the symmetrical arrangement of the in-situ concrete piles (1) on the bottom of the excavation pit to be excavated and the arrangement of the tubular steel columns (2) at the upper end of the respective in-situ concrete piles (1) comprises:Digging pile holes in the bottom of the construction pit and inserting reinforcement cages for the in-situ concrete piles (1) into the pile holes;Placing concrete in the reinforcement cages up to a first design height; andInsertion of the tubular steel columns (2) into the concrete using a hydraulic verticality compensation system, which is poured into corresponding reinforcement cages up to a second design height.
[11]
11. The method according to claim 9, wherein the structure of the platform made of steel (4) which connects all of the tubular steel columns (2) comprises:Connecting all tubular steel columns (2) with a ring carrier; andConnecting horizontal steel girders to the ring girder within the ring girder.
[12]
12. The method according to claim 9, wherein the method, after the construction of the platform (4) made of steel, which connects all of the tubular steel columns (2), further comprises:Connecting steel struts (11) to a bottom of the platform (4) made of steel and the tubular steel columns (2).
[13]
13. The method according to claim 9, wherein the structure of the platform (4) made of steel, which connects all tubular steel columns (2), comprises:Structure of the platform (4) made of steel with recesses, the platform (4) made of steel connecting all tubular steel columns (2);wherein the platform (4) made of steel is a platform for a crane (9); andthe recesses being designed so that a clamshell excavator can be lifted with the crane (9) through one of the recesses into the excavation under the platform (4) made of steel.
[14]
14. The method according to claim 9, wherein the lifting devices (5) are bidirectional lifting devices.
[15]
15. The method according to claim 9, wherein the steel brackets (8) are arranged on the inner wall of the open caisson (7) so that the steel brackets (8) are aligned with the respective tubular connecting columns (6), and those with an identical tubular Connecting column (6) to be connected steel brackets (8) are axially spaced along the open caisson (7), also comprising:Providing the steel brackets (8) each having an L-shaped structure composed of a first plate and a second plate connected to the first plate;Attaching the first plates to the inner wall of the open caisson (7); andSupporting the steel consoles (8) on the tubular connecting columns (6), wherein the supporting comprises supporting the second plates on the tubular connecting columns (6).
[16]
16. The method of claim 15, further comprising: prior to supporting the second plates on the tubular connecting columns (6),Attaching horizontal reinforcement members (10) at one end to the first panels; andafter supporting the second plates on the tubular connecting columns (6), pressing the horizontal reinforcing elements (10) at the other end against side surfaces of the tubular connecting columns (6).
[17]
17. The method of claim 15, wherein after supporting the steel brackets (8) on the tubular connecting columns (6), the method further comprises:Providing displacement and force sensors on each of the lifting devices (5); andConnecting the lifting devices (5) and the displacement and force sensors to a controller;wherein the control detects displacements of the tubular connecting columns (6) by the displacement sensors, and if there is a difference between the displacements, the control controls the lifting devices (5) to force the tubular connecting columns (6) on according to the data from the force sensors adjust the height of the bidirectional lifting devices (5).
类似技术:
公开号 | 公开日 | 专利标题
CH715226B1|2021-05-14|Open caisson construction structure and method.
EP1634999B1|2007-06-13|Reinforced concrete column in a ground excavation and method for building said column
DE102009020517B3|2010-10-21|Method of constructing an underground structure
EP2698476B1|2015-08-12|Method for the construction of an offshore structure and foundation for an offshore structure
EP3502352A1|2019-06-26|Polygonal sprout system with nodes for reinforcing excavations
CN107035159A|2017-08-11|A kind of method suitable for frame structure isolated footing building underground increasing layer
WO2004020745A1|2004-03-11|Foundation for water structures
JP2596798B2|1997-04-02|Existing building seismic isolation method
EP2803786B1|2016-04-13|Assembly and repair device
DE2829712C2|1980-07-17|Process for the production of underground structures
EP3303711B1|2021-04-14|Method for constructing a foundation for a tower structure, and onshore tower structure
DE202021103023U1|2021-07-30|A complete positioning and assembly structure for double-walled steel box dams and short groups of protective tubes
Marchand1993|A DEEP BASEMENT IN ALDERSGATE STREET, LONDON. PART 1: CONTRACTOR'S DESIGN AND PLANNING.
DE3631686C2|1989-09-28|
EP1878857A2|2008-01-16|Foundation for gravestones and funerary monuments
CN211395691U|2020-09-01|Structure for improving vertical supporting node
DE4027181C2|1997-06-26|Process for changing the inclination of a building
EP2511223B1|2014-06-11|Method for producing a lifting device in the ground and use of same
CN208517947U|2019-02-19|Steel pipe column can be recycled in combined type
DE102019217692A1|2020-05-20|Foundation for a tower of a wind turbine
DE202019100752U1|2019-02-28|shoring
DE3716750A1|1988-12-01|Method of constructing and sinking foundation structures
AU2016102394A4|2019-05-16|A method of constructing a column, a subterranean structure, and a structure made from the method
DE102005001422A1|2006-07-20|Sinking pits or wells involves filling concrete in shell, compressing, removing soil to let concrete lower, introducing/compressing more concrete, removing more soil to let concrete, repeating until shaft at required depth, removing shell
DE2942428A1|1981-04-30|New or existing harbour wall reinforcement - has submerged pile wall built from elements and intervening drilled tubes
同族专利:
公开号 | 公开日
CN108086340B|2020-02-14|
JP6830748B2|2021-02-17|
CN108086340A|2018-05-29|
JP2020522635A|2020-07-30|
WO2019128155A1|2019-07-04|
引用文献:
公开号 | 申请日 | 公开日 | 申请人 | 专利标题

JPH0474489B2|1984-03-02|1992-11-26|
JP2008231810A|2007-03-22|2008-10-02|Ps Mitsubishi Construction Co Ltd|Underground structure construction method|
CN101503879B|2009-03-10|2012-06-13|中国一冶集团有限公司|Pre-control method for preventing inclination of sinking well|
CN102900090A|2011-07-29|2013-01-30|邹宗煊|Non-inclined dry-operation open caisson capable of preventing water burst and land subsidence and construction method thereof|
CN107100183B|2017-04-19|2019-08-16|张士普|Open caisson builds engineering method|
CN207828995U|2017-12-29|2018-09-07|上海建工二建集团有限公司|Open caisson construction structure|
CN108086340B|2017-12-29|2020-02-14|上海建工二建集团有限公司|Open caisson construction structure and construction method thereof|CN108086340B|2017-12-29|2020-02-14|上海建工二建集团有限公司|Open caisson construction structure and construction method thereof|
CN109252533B|2018-09-17|2022-01-25|中国一冶集团有限公司|Open caisson sinking control system and construction method thereof|
CN108999205A|2018-09-28|2018-12-14|北京首钢建设集团有限公司|A kind of basis fluting retaining wall uses the construction method of rectangular steel plates circle|
CN109826218A|2019-03-25|2019-05-31|中国十七冶集团有限公司|A kind of open caisson end heavy stage hydraulic lifting deviation-rectifying system|
CN110747876A|2019-09-11|2020-02-04|中铁上海工程局集团有限公司|Auxiliary device for sinking in open caisson construction and operation method thereof|
法律状态:
优先权:
申请号 | 申请日 | 专利标题
CN201711468686.7A|CN108086340B|2017-12-29|2017-12-29|Open caisson construction structure and construction method thereof|
PCT/CN2018/092434|WO2019128155A1|2017-12-29|2018-06-22|Open caisson construction structure and method|
[返回顶部]